Skip to main content
Sarkari MCQs Government Exam Question Bank
Menu
Question no. 56102

P installs railway tracks between two stations in 16 days and Q in 12 days. Aided by R, they finish the task in 4 days. How many days would R require working alone?

Select your answer for: P installs railway tracks between two stations in 16 days and Q in 12 days. Aided by R, they finish the task in 4 days. How many days would R require working alone?
Show answer

Answer: A. 9(3/5) days

Explanation

Individual work rates for p and q are one sixteenth and one twelfth respectively. Combined work rate for p, q, and r together is one quarter per day. Subtracting p and q rates from the total gives r rate as five forty eighths, equaling nine point six days. Collaborative work rates are additive when multiple agents contribute simultaneously. Reciprocal conversion turns daily work output fractions back into total completion days. Fractions convert into mixed number time formats like nine and three fifths days.

Construction managers calculate individual contractor timelines for phased building projects. Project schedulers determine labor requirements by summing individual productivity rates. Engineering teams allocate task responsibilities to meet strict project delivery deadlines. Option B underestimates the required days due to an arithmetic subtraction error. Option C miscalculates the fractional work rate for the third contributor. Option D rounds the completion time incorrectly to a full integer value.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. Mr. Tassawar Javed invested Rs. 13,900 across schemes A and B at simple interest rates of 14% p.a. and 11% p.a. respectively. Given the total simple interest after 2 years is Rs. 3508, what sum was placed in Scheme B?

Select your answer for: Mr. Tassawar Javed invested Rs. 13,900 across schemes A and B at simple interest rates of 14% p.a. and 11% p.a. respectively. Given the total simple interest after 2 years is Rs. 3508, what sum was placed in Scheme B?
Show answer

Answer: A. Rs. 6400

Thirteen thousand nine hundred is invested across schemes A and B at fourteen and eleven percent simple interest. The total simple interest earned after two years is three thousand five hundred eight. Setting up a weight...

Q2. P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?

Select your answer for: P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?
Show answer

Answer: C. 18

Individual work rates for worker pairs are established by inverting their respective completion days. After working together for ten days, a specific fraction of the total project is successfully completed. Subtracting t...

Q3. P accomplishes a task in the exact duration Q and R need combined. P and Q finish it together in 10 days, whereas R alone takes 50 days. How many days will Q require independently__________?

Select your answer for: P accomplishes a task in the exact duration Q and R need combined. P and Q finish it together in 10 days, whereas R alone takes 50 days. How many days will Q require independently__________?
Show answer

Answer: B. 25 days

P's work rate equals the combined rate of Q and R operating together. R alone takes fifty days, meaning R completes one fiftieth of the task per day. Combining individual and joint rates in a system of equations gives Q...

Q4. Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.

Select your answer for: Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.
Show answer

Answer: C. 1% loss

Oranges are purchased at eleven per rupee and an equal quantity at nine per rupee. Retailing the entire combined lot at ten per rupee results in a cost price exceeding total revenue. Slight discrepancies between harmonic...

Q5. P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.

Select your answer for: P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.
Show answer

Answer: A. 12

Workers P and Q complete a combined portion of the task during the first two days of joint effort. After Q departs, worker P continues alone to finish the remaining fractional workload. Adding the initial two days of joi...

Q6. A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?

Select your answer for: A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?
Show answer

Answer: A. 12 sq m

The Pythagorean theorem relates rectangle length, breadth, and diagonal measurements. Squaring the diagonal five and subtracting squared breadth four gives squared length nine. The length equals three meters, which multi...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test