Question no. 56103

One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?

Select your answer for: One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?
Show answer

Answer: C. 144 min

Explanation

The correct answer is one hundred forty-four minutes for the slower pipe alone. The faster pipe takes x minutes while the slower pipe takes three times x minutes. Solving their combined rate equation yields forty-eight for x, making the slower pipe one hundred forty-four. Pipe filling problems use reciprocal rates of work to determine combined completion times. The combined rate of both pipes equals one over thirty-six of the reservoir per minute. One over three x plus one over x equals one over thirty-six sets up the equation.

Plumbing and municipal water treatment plants use pipe flow rates to design distribution networks. Hydraulic engineering relies on rate equations to prevent system overflow and dry reservoirs. Aquarium maintenance technicians calculate pump flow rates using similar inverse time formulas. Option A underestimates the slower pipe duration by solving the rate equation incorrectly. Option B results from an arithmetic miscalculation during the algebraic fraction simplification. Option D overestimates the required time by applying an incorrect multiplier to x.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?

Select your answer for: P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?
Show answer

Answer: C. 18

Individual work rates for worker pairs are established by inverting their respective completion days. After working together for ten days, a specific fraction of the total project is successfully completed. Subtracting t...

Q2. P accomplishes a task in the exact duration Q and R need combined. P and Q finish it together in 10 days, whereas R alone takes 50 days. How many days will Q require independently__________?

Select your answer for: P accomplishes a task in the exact duration Q and R need combined. P and Q finish it together in 10 days, whereas R alone takes 50 days. How many days will Q require independently__________?
Show answer

Answer: B. 25 days

P's work rate equals the combined rate of Q and R operating together. R alone takes fifty days, meaning R completes one fiftieth of the task per day. Combining individual and joint rates in a system of equations gives Q...

Q3. P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?

Select your answer for: P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?
Show answer

Answer: B. 10 days

P works alone for four days at a rate of one twentieth per day, completing one fifth of the total task. The remaining four fifths of the work is finished by P and Q together at a combined rate. Combining individual rates...

Q4. P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.

Select your answer for: P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.
Show answer

Answer: A. 12

Workers P and Q complete a combined portion of the task during the first two days of joint effort. After Q departs, worker P continues alone to finish the remaining fractional workload. Adding the initial two days of joi...

Q5. A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?

Select your answer for: A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?
Show answer

Answer: A. 12 sq m

The Pythagorean theorem relates rectangle length, breadth, and diagonal measurements. Squaring the diagonal five and subtracting squared breadth four gives squared length nine. The length equals three meters, which multi...

Q6. p is six times greater than q. By what percentage is q smaller than p:________?

Select your answer for: p is six times greater than q. By what percentage is q smaller than p:________?
Show answer

Answer: A. 83 1/3

If p is six times greater than q, p equals six times q according to standard algebraic phrasing. The difference between p and q represents five parts when q is treated as one baseline unit. Dividing the difference by p g...