Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.
Show answer Hide answer
Answer: C. 1% loss
Explanation
Oranges are purchased at eleven per rupee and an equal quantity at nine per rupee. Retailing the entire combined lot at ten per rupee results in a cost price exceeding total revenue. Slight discrepancies between harmonic means of purchase prices and selling prices generate a one percent loss. Equal quantity purchases at different unit prices result in an average cost equal to the harmonic mean. Purchasing at eleven and nine gives an average cost price slightly higher than ten per rupee. When average cost exceeds selling price, the transaction yields a net financial loss percentage.
Merchants evaluate average unit costs when combining inventory batches purchased at different wholesale rates. Retail pricing strategies require careful tracking of blended cost bases to avoid unexpected financial losses. Commercial arithmetic puzzles test understanding of average pricing and loss calculations. Option A incorrectly suggests a gain instead of accounting for the harmonic mean cost discrepancy. Option B proposes a two percent gain, contradicting the actual cost-revenue calculation. Option D suggests a two percent loss, overstating the minor mathematical deficit in the transaction.
- Subject
- Mathematics
- Category
- Mathematics
- Topic
- —
- Difficulty
- medium
Related questions
Q1. P accomplishes a task in the exact duration Q and R need combined. P and Q finish it together in 10 days, whereas R alone takes 50 days. How many days will Q require independently__________?
Show answer Hide answer
Answer: B. 25 days
P's work rate equals the combined rate of Q and R operating together. R alone takes fifty days, meaning R completes one fiftieth of the task per day. Combining individual and joint rates in a system of equations gives Q...
Q2. P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?
Show answer Hide answer
Answer: B. 10 days
P works alone for four days at a rate of one twentieth per day, completing one fifth of the total task. The remaining four fifths of the work is finished by P and Q together at a combined rate. Combining individual rates...
Q3. P installs railway tracks between two stations in 16 days and Q in 12 days. Aided by R, they finish the task in 4 days. How many days would R require working alone?
Show answer Hide answer
Answer: A. 9(3/5) days
Individual work rates for p and q are one sixteenth and one twelfth respectively. Combined work rate for p, q, and r together is one quarter per day. Subtracting p and q rates from the total gives r rate as five forty ei...
Q4. A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?
Show answer Hide answer
Answer: A. 12 sq m
The Pythagorean theorem relates rectangle length, breadth, and diagonal measurements. Squaring the diagonal five and subtracting squared breadth four gives squared length nine. The length equals three meters, which multi...
Q5. p is six times greater than q. By what percentage is q smaller than p:________?
Show answer Hide answer
Answer: A. 83 1/3
If p is six times greater than q, p equals six times q according to standard algebraic phrasing. The difference between p and q represents five parts when q is treated as one baseline unit. Dividing the difference by p g...
Q6. P, Q, and R finish a project in 24, 6, and 12 days respectively. Working collectively, the task will be finished in________days.
Show answer Hide answer
Answer: B. 3 3⁄7
Individual work rates for p, q, and r are one twenty fourth, one sixth, and one twelfth. Summing these fractions gives a combined work rate of seven twenty fourths per day. Inverting this combined rate yields twenty four...