Question no. 56108

P, Q, and R finish a project in 24, 6, and 12 days respectively. Working collectively, the task will be finished in________days.

Select your answer for: P, Q, and R finish a project in 24, 6, and 12 days respectively. Working collectively, the task will be finished in________days.
Show answer

Answer: B. 3 3⁄7

Explanation

Individual work rates for p, q, and r are one twenty fourth, one sixth, and one twelfth. Summing these fractions gives a combined work rate of seven twenty fourths per day. Inverting this combined rate yields twenty four sevenths, which simplifies to three and three sevenths days. Combined work rates sum individual unit productivity fractions together. Inverting the sum of work rates calculates total collaborative project duration. Mixed numbers express fractional completion times in accessible everyday units.

Project teams combine member productivity rates to estimate joint task completion times. Manufacturing supervisors calculate assembly line output speeds using worker collaboration data. Contractors schedule multi worker tasks to optimize labor efficiency on sites. Option A underestimates total collaborative days by miscalculating rate sums. Option C overestimates the time required for the collective team to finish. Option D rounds the completion time incorrectly to a whole number of days.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.

Select your answer for: Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.
Show answer

Answer: C. 1% loss

Oranges are purchased at eleven per rupee and an equal quantity at nine per rupee. Retailing the entire combined lot at ten per rupee results in a cost price exceeding total revenue. Slight discrepancies between harmonic...

Q2. P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.

Select your answer for: P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.
Show answer

Answer: A. 12

Workers P and Q complete a combined portion of the task during the first two days of joint effort. After Q departs, worker P continues alone to finish the remaining fractional workload. Adding the initial two days of joi...

Q3. A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?

Select your answer for: A rectangular field has a 4 m breadth and a 5 m diagonal length. What is its total area?
Show answer

Answer: A. 12 sq m

The Pythagorean theorem relates rectangle length, breadth, and diagonal measurements. Squaring the diagonal five and subtracting squared breadth four gives squared length nine. The length equals three meters, which multi...

Q4. P, Q, and R complete a task in 20, 30, and 60 days respectively. How many days are needed if P works continuously with assistance from Q and R every third day?

Select your answer for: P, Q, and R complete a task in 20, 30, and 60 days respectively. How many days are needed if P works continuously with assistance from Q and R every third day?
Show answer

Answer: C. 15 days

P, Q, and R complete the task in twenty, thirty, and sixty days, establishing individual daily work rates. P works every day while Q and R assist every third day, forming a repeating three-day work cycle. This cooperativ...

Q5. P works twice as fast as Q. Given Q alone finishes a task in 12 days, how many days will P and Q require combined________days

Select your answer for: P works twice as fast as Q. Given Q alone finishes a task in 12 days, how many days will P and Q require combined________days
Show answer

Answer: D. 4

Worker Q finishes the task alone in twelve days, which means P takes half that time at six days. The individual work rates are one twelfth for Q and one sixth for P. Adding their rates gives three twelfths, simplifying t...

Q6. P is 30% more productive than Q and finishes a task in 23 days. How much time do they need working together?

Select your answer for: P is 30% more productive than Q and finishes a task in 23 days. How much time do they need working together?
Show answer

Answer: D. 13

Q takes twenty-three days, and P is thirty percent more productive, taking twenty-three over one point three. Combining P and Q work rates provides their joint daily output fraction. Inverting the combined daily rate yie...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test