Question no. 56111

P works twice as fast as Q. Given Q alone finishes a task in 12 days, how many days will P and Q require combined________days

Select your answer for: P works twice as fast as Q. Given Q alone finishes a task in 12 days, how many days will P and Q require combined________days
Show answer

Answer: D. 4

Explanation

Worker Q finishes the task alone in twelve days, which means P takes half that time at six days. The individual work rates are one twelfth for Q and one sixth for P. Adding their rates gives three twelfths, simplifying to one fourth, which means four days combined. Efficiency ratios state that working twice as fast cuts the required completion time in half. Combined work rates equal the sum of individual reciprocal completion times for all active workers. Inverting the combined work rate fraction yields the total number of days required for completion.

Resource allocation models assign faster workers to tasks to minimize overall project completion schedules. Hiring decisions in contracting rely on productivity multipliers to estimate team completion speeds. Manufacturing efficiency metrics compare worker output speeds to optimize labor force deployments. Option A severely underestimates the required time by miscalculating the sum of unit fractions. Option B represents a premature calculation step rather than the final combined completion time. Option C results from an error when adding the individual fractional work rates together.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. p is six times greater than q. By what percentage is q smaller than p:________?

Select your answer for: p is six times greater than q. By what percentage is q smaller than p:________?
Show answer

Answer: A. 83 1/3

If p is six times greater than q, p equals six times q according to standard algebraic phrasing. The difference between p and q represents five parts when q is treated as one baseline unit. Dividing the difference by p g...

Q2. P, Q, and R finish a project in 24, 6, and 12 days respectively. Working collectively, the task will be finished in________days.

Select your answer for: P, Q, and R finish a project in 24, 6, and 12 days respectively. Working collectively, the task will be finished in________days.
Show answer

Answer: B. 3 3⁄7

Individual work rates for p, q, and r are one twenty fourth, one sixth, and one twelfth. Summing these fractions gives a combined work rate of seven twenty fourths per day. Inverting this combined rate yields twenty four...

Q3. P finishes a project in 15 days and Q in 20 days. After collaborating for 4 days, what proportion of the work remains unfinished?

Select your answer for: P finishes a project in 15 days and Q in 20 days. After collaborating for 4 days, what proportion of the work remains unfinished?
Show answer

Answer: A. 8/15

The correct answer is eight-fifteenths for the proportion of work remaining unfinished. P and Q complete seven-fifteenths of the project during their four days of collaboration. Subtracting seven-fifteenths from one whol...

Q4. P and Q launched a venture contributing Rs. 4 lakhs and Rs. 10 lakhs respectively. P draws a monthly salary of Rs. 5000 for managing operations. If the annual profit reached Rs. 2 lakhs, what is the earnings ratio between them?

Select your answer for: P and Q launched a venture contributing Rs. 4 lakhs and Rs. 10 lakhs respectively. P draws a monthly salary of Rs. 5000 for managing operations. If the annual profit reached Rs. 2 lakhs, what is the earnings ratio between them?
Show answer

Answer: D. 1 : 1

P draws a monthly management salary which is deducted from the annual profit pool before distribution. After accounting for management compensation, the remaining profit is divided between partners based on capital. Adju...

Q5. What fraction of an 80-member faculty remains after 20 teachers are reassigned?

Select your answer for: What fraction of an 80-member faculty remains after 20 teachers are reassigned?
Show answer

Answer: D. 75

Starting faculty count equals eighty members before any reassignment actions occur. Reassigning twenty teachers leaves sixty faculty members remaining at the institution. The remaining count equals sixty teachers out of...

Q6. P, Q, and R share a sum of Rs.6000. If R holds two-thirds of the combined total of P and Q, what is R's share?

Select your answer for: P, Q, and R share a sum of Rs.6000. If R holds two-thirds of the combined total of P and Q, what is R's share?
Show answer

Answer: C. Rs.2400

The correct answer is two thousand four hundred rupees for R's share. R holds two-thirds of the combined total of P and Q according to the problem. This means R's share equals two-fifths of the total six thousand rupees...