Question no. 56101

P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?

Select your answer for: P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?
Show answer

Answer: B. 10 days

Explanation

P works alone for four days at a rate of one twentieth per day, completing one fifth of the total task. The remaining four fifths of the work is finished by P and Q together at a combined rate. Combining individual rates shows that P and Q finish the remaining work in six days, totaling ten days. Sequential work problems require calculating progress made during solo work periods before adding joint work durations. Individual work rates are represented as unit fractions corresponding to the time needed to finish a full job. Adding individual rates gives the joint productivity speed for workers operating simultaneously on the same task.

Option A underestimates the total duration by ignoring the work completed during the joint phase. Option C overestimates the total duration by miscalculating the combined work rate of both individuals. Option D represents an incorrect time total that fails to match the combined work equations.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. Out of 10 project workers, 4 possess degrees. If 3 individuals are picked, what is the likelihood that at least one of them is a graduate?

Select your answer for: Out of 10 project workers, 4 possess degrees. If 3 individuals are picked, what is the likelihood that at least one of them is a graduate?
Show answer

Answer: D. 5/6

The correct answer is five-sixths probability that at least one worker is a graduate. The probability of choosing no graduates is calculated using combinations of non-graduates. Subtracting the zero-graduate probability...

Q2. Mr. Tassawar Javed invested Rs. 13,900 across schemes A and B at simple interest rates of 14% p.a. and 11% p.a. respectively. Given the total simple interest after 2 years is Rs. 3508, what sum was placed in Scheme B?

Select your answer for: Mr. Tassawar Javed invested Rs. 13,900 across schemes A and B at simple interest rates of 14% p.a. and 11% p.a. respectively. Given the total simple interest after 2 years is Rs. 3508, what sum was placed in Scheme B?
Show answer

Answer: A. Rs. 6400

Thirteen thousand nine hundred is invested across schemes A and B at fourteen and eleven percent simple interest. The total simple interest earned after two years is three thousand five hundred eight. Setting up a weight...

Q3. P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?

Select your answer for: P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?
Show answer

Answer: C. 18

Individual work rates for worker pairs are established by inverting their respective completion days. After working together for ten days, a specific fraction of the total project is successfully completed. Subtracting t...

Q4. One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?

Select your answer for: One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?
Show answer

Answer: C. 144 min

The correct answer is one hundred forty-four minutes for the slower pipe alone. The faster pipe takes x minutes while the slower pipe takes three times x minutes. Solving their combined rate equation yields forty-eight f...

Q5. Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.

Select your answer for: Oranges are purchased at 11 per rupee, with an equal quantity bought at 9 per rupee. If the entire lot is retailed at 10 per rupee, determine the percentage of profit or loss.
Show answer

Answer: C. 1% loss

Oranges are purchased at eleven per rupee and an equal quantity at nine per rupee. Retailing the entire combined lot at ten per rupee results in a cost price exceeding total revenue. Slight discrepancies between harmonic...

Q6. P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.

Select your answer for: P and Q finish a task in 15 days and 10 days respectively. Starting together, Q departs after 2 days while P finishes the rest. The entire task took__________days.
Show answer

Answer: A. 12

Workers P and Q complete a combined portion of the task during the first two days of joint effort. After Q departs, worker P continues alone to finish the remaining fractional workload. Adding the initial two days of joi...