P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?

Select your answer for: P and Q finish a task in 30 days, Q and R in 24 days, and R and P in 20 days. After working together for 10 days, Q and R depart. How many additional days will P require to complete the task?
Show answer

Answer: C. 18

Explanation

Individual work rates for worker pairs are established by inverting their respective completion days. After working together for ten days, a specific fraction of the total project is successfully completed. Subtracting the completed work leaves P to finish the remaining workload alone in eighteen days. Work rate problems assume that productivity is inversely proportional to the time taken to finish a task. Simultaneous work contributions are added together to find cumulative project completion progress over time. Remaining work fractions determine how many additional days an individual worker needs to finish.

Construction scheduling requires calculating how remaining workers complete projects after partner departures. Factory production planning adjusts labor allocations when machine operators finish shifts at staggered intervals. Team project management involves tracking individual contributions to ensure timely milestone delivery. Option A underestimates the remaining time P needs to finish the rest of the project alone. Option B incorrectly calculates the remaining workload fraction left after the initial ten days. Option D overestimates the required days by miscalculating P's individual work rate capacity.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. Nawaz Sahrif allots 10% of his earnings to house rent, 25% of the remainder to miscellaneous expenses, and 20% of the remaining amount to his children's education. If he is left with Rs. 1944, what is his total income_______?

Select your answer for: Nawaz Sahrif allots 10% of his earnings to house rent, 25% of the remainder to miscellaneous expenses, and 20% of the remaining amount to his children's education. If he is left with Rs. 1944, what is his total income_______?
Show answer

Answer: A. Rs.3600

Deductions occur sequentially for house rent, miscellaneous expenses, and children education. Working backward from nineteen forty four reverses each successive percentage deduction. Dividing and multiplying through thes...

Q2. A single number is chosen at random from the first 20 natural numbers. What is the probability that it proves to be either even or prime_____________?

Select your answer for: A single number is chosen at random from the first 20 natural numbers. What is the probability that it proves to be either even or prime_____________?
Show answer

Answer: D. 17/20

Among the first 20 natural numbers, 10 are even and 8 are prime, with 4 numbers being both. Applying inclusion-exclusion gives 14 favorable outcomes out of 20, which simplifies to 17/20.

Q3. Out of 10 project workers, 4 possess degrees. If 3 individuals are picked, what is the likelihood that at least one of them is a graduate?

Select your answer for: Out of 10 project workers, 4 possess degrees. If 3 individuals are picked, what is the likelihood that at least one of them is a graduate?
Show answer

Answer: D. 5/6

The correct answer is five-sixths probability that at least one worker is a graduate. The probability of choosing no graduates is calculated using combinations of non-graduates. Subtracting the zero-graduate probability...

Q4. P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?

Select your answer for: P and Q finish a job in 20 days and 12 days respectively. P begins alone, and Q joins him after 4 days until completion. What was the total duration of the work?
Show answer

Answer: B. 10 days

P works alone for four days at a rate of one twentieth per day, completing one fifth of the total task. The remaining four fifths of the work is finished by P and Q together at a combined rate. Combining individual rates...

Q5. P installs railway tracks between two stations in 16 days and Q in 12 days. Aided by R, they finish the task in 4 days. How many days would R require working alone?

Select your answer for: P installs railway tracks between two stations in 16 days and Q in 12 days. Aided by R, they finish the task in 4 days. How many days would R require working alone?
Show answer

Answer: A. 9(3/5) days

Individual work rates for p and q are one sixteenth and one twelfth respectively. Combined work rate for p, q, and r together is one quarter per day. Subtracting p and q rates from the total gives r rate as five forty ei...

Q6. One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?

Select your answer for: One pipe fills a reservoir three times quicker than another. Operating together, they fill it in 36 min; how long would the slower pipe take alone?
Show answer

Answer: C. 144 min

The correct answer is one hundred forty-four minutes for the slower pipe alone. The faster pipe takes x minutes while the slower pipe takes three times x minutes. Solving their combined rate equation yields forty-eight f...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test