Question no. 57938

Queuing theory models are applied in practice to analyze____________________?

Select your answer for: Queuing theory models are applied in practice to analyze____________________?
Show answer

Answer: D. all of the above

Explanation

Queuing theory utilizes mathematical probability models to analyze waiting lines, service rates, and customer congestion patterns. These versatile mathematical models apply equally well to inventory control problems, highway traffic congestion, and job-shop scheduling. Any operational scenario involving arrivals, waiting queues, and service facilities can be successfully evaluated using queuing theory. Agner Krarup Erlang originally developed queuing theory to solve telephone traffic congestion problems for Copenhagen telephone exchanges. Queuing models use statistical distributions such as Poisson arrivals and exponential service times to simulate real-world congestion. Industrial engineering applies these models to optimize service counter staffing, machine repair crews, and automated warehouse routing.

Option A is incomplete because queuing theory applies to much more than just inventory problems within industrial facilities. Option B is too narrow since traffic studies represent only one of many practical applications for waiting-line mathematics. Option C is also a partial application because job-shop scheduling represents just one specific domain addressed by queuing models.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The simplex algorithm serves as the foundational mathematical method for__________________?

Select your answer for: The simplex algorithm serves as the foundational mathematical method for__________________?
Show answer

Answer: C. linear programming

The simplex algorithm is a standard iterative mathematical procedure used to solve linear programming optimization problems. Linear programming models maximize or minimize objective functions subject to linear constraint...

Q2. An incentive plan where a standard completion time is set and workers earn a bonus for every hour saved below that benchmark is known as_________________?

Select your answer for: An incentive plan where a standard completion time is set and workers earn a bonus for every hour saved below that benchmark is known as_________________?
Show answer

Answer: D. Halsey Premium plan

The Halsey Premium plan sets a standard completion time and awards workers a bonus for time saved. Workers receive their guaranteed hourly wage plus an extra financial percentage for finishing early. This premium incenti...

Q3. Time studies aim to establish the duration required to perform a task by_______________?

Select your answer for: Time studies aim to establish the duration required to perform a task by_______________?
Show answer

Answer: B. average worker

Time studies establish task durations by observing a qualified average worker performing operations. Rating factors are applied to adjust observed times to match normal worker paces. Evaluating an average worker ensures...

Q4. Travel charts furnish planners with data regarding__________________?

Select your answer for: Travel charts furnish planners with data regarding__________________?
Show answer

Answer: B. a compact estimate of the handling which must be done between various work sections

Travel charts provide a compact matrix summary of material handling volumes between various work sections. Tabulating inter-departmental movement frequencies on a travel chart helps visualize plant material flow patterns...

Q5. The operational time that yields the absolute minimum direct cost for an activity is recognized as________________?

Select your answer for: The operational time that yields the absolute minimum direct cost for an activity is recognized as________________?
Show answer

Answer: B. slow time

Crash time represents the absolute shortest duration possible to complete a given activity successfully. Slow time or normal time settings carry different cost implications for project managers. Accelerating an activity...

Q6. In methods-time measurement, the acronym TMU expands to__________________?

Select your answer for: In methods-time measurement, the acronym TMU expands to__________________?
Show answer

Answer: B. time measurement unit

In methods-time measurement, the acronym TMU officially expands to time measurement unit. Time measurement units provide a standardized numerical scale for evaluating manual motions. Conversion factors link these special...