Question no. 57935

An incentive plan where a standard completion time is set and workers earn a bonus for every hour saved below that benchmark is known as_________________?

Select your answer for: An incentive plan where a standard completion time is set and workers earn a bonus for every hour saved below that benchmark is known as_________________?
Show answer

Answer: D. Halsey Premium plan

Explanation

The Halsey Premium plan sets a standard completion time and awards workers a bonus for time saved. Workers receive their guaranteed hourly wage plus an extra financial percentage for finishing early. This premium incentive system shares the financial savings of time reduction between labor and management. Frederick Halsey introduced this incentive model to reward speed without cutting base hourly rates. Bonuses are typically calculated as a fraction of the time saved multiplied by the hourly wage rate. The plan provides steady motivation for workers to improve output speed on repetitive factory tasks.

Manufacturing facilities implement the Halsey plan to encourage higher productivity and lower labor costs. Workers benefit from earning extra money while employers enjoy reduced overhead per manufactured unit. Understanding various wage incentive plans helps industrial engineers design fair compensation structures. The Rowan plan calculates bonuses as a variable percentage of time saved rather than a fixed fraction. The Bedaux plan measures work in point units representing standard minutes of labor and rest. Taylor Differential Piece rate systems penalize slow workers with lower rates rather than offering premiums.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Project scheduling provides management with crucial data concerning____________________?

Select your answer for: Project scheduling provides management with crucial data concerning____________________?
Show answer

Answer: A. when work should start and how much work should be completed during a certain period

Project scheduling provides management with crucial data regarding project timelines. It specifies exactly when work should start and how much work is expected. This enables managers to track progress across specific ope...

Q2. The specific time span by which an activity's completion can be delayed without postponing the start of successor tasks is termed_________________?

Select your answer for: The specific time span by which an activity's completion can be delayed without postponing the start of successor tasks is termed_________________?
Show answer

Answer: C. free float

Free float measures the exact time span an activity can be delayed without postponing the earliest start date of any successor task. This specific float calculation allows project schedulers to absorb minor operational d...

Q3. Executing a specific defined task within the CPM framework is referred to as______________________?

Select your answer for: Executing a specific defined task within the CPM framework is referred to as______________________?
Show answer

Answer: C. activity

Within the Critical Path Method framework, executing a specific defined task is referred to as an activity. Activities consume both time and tangible resources while transforming inputs into project deliverables. Network...

Q4. Industrial time study is defined as__________________?

Select your answer for: Industrial time study is defined as__________________?
Show answer

Answer: A. the appraisal, in terms of time, of the value of work involving human effort

Industrial time study directly evaluates the time value of human work effort to establish standards. This systematic observation helps management measure productivity and set realistic production quotas for workers. Dete...

Q5. Queuing theory models are applied in practice to analyze____________________?

Select your answer for: Queuing theory models are applied in practice to analyze____________________?
Show answer

Answer: D. all of the above

Queuing theory utilizes mathematical probability models to analyze waiting lines, service rates, and customer congestion patterns. These versatile mathematical models apply equally well to inventory control problems, hig...

Q6. The single most important objective underlying proper plant layout design is_____________________?

Select your answer for: The single most important objective underlying proper plant layout design is_____________________?
Show answer

Answer: A. overall simplification, safety of integration

The single most important objective underlying proper plant layout design is overall process simplification and safe integration. Simplifying material flow and ensuring safe workspace integration maximizes manufacturing...