The industrial expediting function entails maintaining continuous oversight of__________________?
Show answer Hide answer
Answer: B. flow of material and in case of trouble locate source of trouble
Explanation
Industrial expediting maintains continuous oversight of material flow to quickly locate and resolve operational bottlenecks. Expediters track component deliveries and production progress to prevent manufacturing delays before they happen. When trouble arises in the supply chain, expediting personnel immediately identify the root source of delay. Production control requires active monitoring of raw material inputs and work-in-progress inventories across factories. Expediting bridges the gap between purchasing, inventory management, and shop floor scheduling operations. Timely intervention by expediters keeps manufacturing projects on schedule and avoids costly idle time.
Manufacturing facilities use industrial expediting to ensure critical parts arrive at assembly workstations on time. Supply chain disruptions are mitigated when expediting personnel proactively track delayed shipments and components. Efficient material flow management reduces overall manufacturing lead times and improves customer satisfaction. Monitoring operator activity describes direct supervision and time study work rather than industrial expediting functions. Minimizing delays is a general goal, but tracking material flow and locating trouble is the specific expediting action. Making efficient dispatching focuses on routing and scheduling orders rather than tracking delinquent material flows.
- Subject
- Engineering
- Category
- Mechanical Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Achieving an optimum project schedule implies that_______________?
Show answer Hide answer
Answer: B. lowest possible cost and shortest possible time for project
An optimum project schedule achieves the lowest possible cost and the shortest possible time for execution. Project crashing adds direct costs to reduce duration until indirect expenses and crashing costs balance perfect...
Q2. The activity slack or float associated with any node on a PERT/CPM chart is shown by__________________?
Show answer Hide answer
Answer: D. anyone of the above
Activity float or slack can be calculated using various combinations of latest and earliest start/finish times. Total float represents the amount of time an activity can be delayed without delaying the overall project co...
Q3. PERT methodology functions as__________________?
Show answer Hide answer
Answer: B. event oriented technique
PERT methodology focuses primarily on milestone events marking the start or completion of tasks. Network nodes represent these critical events rather than just the working activities themselves. This makes PERT fundament...
Q4. Who is widely recognized as the father of industrial engineering_________________?
Show answer Hide answer
Answer: B. Gnatt
Henry Gantt is renowned for developing the Gantt chart and contributing significantly to industrial management.
Q5. Statistical acceptance sampling procedures are extensively applied in________________?
Show answer Hide answer
Answer: C. mass production
Statistical acceptance sampling procedures are extensively applied in high-volume mass production manufacturing environments. Inspected lots contain thousands of identical items making complete 100% inspection economical...
Q6. The historical figure acknowledged as the father of time study was_________________?
Show answer Hide answer
Answer: A. F.W. Taylor
F.W. Taylor is widely recognized as the father of scientific management and time study. He pioneered systematic workplace observations using stopwatches to analyze worker motions and establish standard times. Taylor's sc...