The historical figure acknowledged as the father of time study was_________________?

Select your answer for: The historical figure acknowledged as the father of time study was_________________?
Show answer

Answer: A. F.W. Taylor

Explanation

F.W. Taylor is widely recognized as the father of scientific management and time study. He pioneered systematic workplace observations using stopwatches to analyze worker motions and establish standard times. Taylor's scientific management principles revolutionized industrial manufacturing efficiency during the late nineteenth and early twentieth centuries. Time study is a work measurement technique used to record the time required to perform specific operational elements. Scientific management sought to replace rule-of-thumb workplace methods with data-driven industrial engineering analysis. Taylor published his groundbreaking management theories in seminal works that laid the foundation for modern industrial engineering.

Option B (H.L. Gantt) is famous for inventing visual production scheduling charts rather than being the father of time study. Option C (F.B. Gilbreth) is renowned as a pioneer of motion study and micromotion analysis rather than primary time study. Options D and E are incorrect because later researchers built upon Taylor's original foundational time study methodologies.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The industrial expediting function entails maintaining continuous oversight of__________________?

Select your answer for: The industrial expediting function entails maintaining continuous oversight of__________________?
Show answer

Answer: B. flow of material and in case of trouble locate source of trouble

Industrial expediting maintains continuous oversight of material flow to quickly locate and resolve operational bottlenecks. Expediters track component deliveries and production progress to prevent manufacturing delays b...

Q2. Urgent emergency rush orders can be processed and expedited most effectively within__________________?

Select your answer for: Urgent emergency rush orders can be processed and expedited most effectively within__________________?
Show answer

Answer: D. intermittent production

Intermittent production systems feature flexible layouts and general-purpose machinery. This operational flexibility allows job shops to handle custom or rush orders efficiently. Emergency orders can be scheduled into in...

Q4. When setting up a product layout, the material handling apparatus must be_________________?

Select your answer for: When setting up a product layout, the material handling apparatus must be_________________?
Show answer

Answer: D. be designed as special purpose for a particular application

A product layout arranges machinery and equipment in a straight sequential production line. Because products move along a fixed path, material handling equipment must be dedicated. Consequently, material handling apparat...

Q5. For large-scale shipbuilding industries, which plant layout is considered most suitable_________________?

Select your answer for: For large-scale shipbuilding industries, which plant layout is considered most suitable_________________?
Show answer

Answer: C. fixed position layout

Fixed position layouts are specifically chosen when the manufactured item is excessively large and heavy to transport. Shipbuilding requires the massive hull to remain stationary while workers and heavy machinery are bro...

Q6. Gantt charts are primarily designed and used for_________________?

Select your answer for: Gantt charts are primarily designed and used for_________________?
Show answer

Answer: B. production schedule

Gantt charts are graphical planning tools primarily designed and used for scheduling production activities over time. Horizontal bars on a Gantt chart display scheduled start and completion dates for various manufacturin...