Question no. 57838

A low per-unit manufacturing cost is achievable through____________________?

Select your answer for: A low per-unit manufacturing cost is achievable through____________________?
Show answer

Answer: A. product layout

Explanation

A product layout arranges machinery in the exact sequence of manufacturing operations. This specialized arrangement minimizes material handling distance and reduces unnecessary transit time. Streamlining the workflow in this manner achieves a low per-unit manufacturing cost. Product layouts are commonly implemented in mass production and assembly line manufacturing environments. Flow continuous production reduces work-in-progress inventory levels and storage requirements. Equipment is dedicated to producing a specific product design with high volume output.

Automotive assembly plants use product layouts to produce high volumes of vehicles efficiently. Minimizing material handling reduces labor costs and speeds up overall production throughput. This layout type requires high capital investment and stable product demand to remain economical. A functional layout groups similar machines together, which increases material travel distances for parts. Automatic material handling equipment aids production but does not replace the efficiency of layouts. Specialization of operation describes labor division rather than the specific plant floor layout type.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The Critical Path Method incorporates how many time estimates for activities__________________

Select your answer for: The Critical Path Method incorporates how many time estimates for activities__________________
Show answer

Answer: A. one time estimate

The standard Critical Path Method uses single-point deterministic time estimates for activities. Each activity is assigned one specific expected duration based on historical data or calculations. This deterministic appro...

Q2. Achieving an optimum project schedule implies that_______________?

Select your answer for: Achieving an optimum project schedule implies that_______________?
Show answer

Answer: B. lowest possible cost and shortest possible time for project

An optimum project schedule achieves the lowest possible cost and the shortest possible time for execution. Project crashing adds direct costs to reduce duration until indirect expenses and crashing costs balance perfect...

Q3. The activity slack or float associated with any node on a PERT/CPM chart is shown by__________________?

Select your answer for: The activity slack or float associated with any node on a PERT/CPM chart is shown by__________________?
Show answer

Answer: D. anyone of the above

Activity float or slack can be calculated using various combinations of latest and earliest start/finish times. Total float represents the amount of time an activity can be delayed without delaying the overall project co...

Q4. Urgent emergency rush orders can be processed and expedited most effectively within__________________?

Select your answer for: Urgent emergency rush orders can be processed and expedited most effectively within__________________?
Show answer

Answer: D. intermittent production

Intermittent production systems feature flexible layouts and general-purpose machinery. This operational flexibility allows job shops to handle custom or rush orders efficiently. Emergency orders can be scheduled into in...

Q6. Statistical acceptance sampling procedures are extensively applied in________________?

Select your answer for: Statistical acceptance sampling procedures are extensively applied in________________?
Show answer

Answer: C. mass production

Statistical acceptance sampling procedures are extensively applied in high-volume mass production manufacturing environments. Inspected lots contain thousands of identical items making complete 100% inspection economical...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test