Skip to main content
Sarkari MCQs Government Exam Question Bank
Menu
Question no. 57837

PERT methodology functions as__________________?

Select your answer for: PERT methodology functions as__________________?
Show answer

Answer: B. event oriented technique

Explanation

PERT methodology focuses primarily on milestone events marking the start or completion of tasks. Network nodes represent these critical events rather than just the working activities themselves. This makes PERT fundamentally an event-oriented probabilistic network scheduling technique. PERT incorporates probabilistic time estimates to account for uncertainty in task durations. Optimistic, most likely, and pessimistic time estimates are combined using statistical formulas. Event scheduling helps managers track major project milestones and intermediate deadlines.

Research and development projects with unpredictable task durations benefit from PERT analysis. Managers use event-oriented networks to report high-level progress to executive stakeholders. Probabilistic scheduling reduces the risk of missing critical program completion dates. Option A is too broad because many scheduling tools manage time effectively. Option C incorrectly categorizes PERT as activity-oriented, which aligns closer with CPM. Option D and E use non-standard terminology that does not define the network methodology.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Basic motion time systems quantify fundamental human motions in units equal to ten-thousandths of_______________?

Select your answer for: Basic motion time systems quantify fundamental human motions in units equal to ten-thousandths of_______________?
Show answer

Answer: B. minute

Predetermined motion time systems quantify fundamental human motions in Time Measurement Units equal to ten-thousandths of an hour. One TMU is specifically defined as zero point zero zero zero zero six hours, which equal...

Q2. The Critical Path Method incorporates how many time estimates for activities__________________

Select your answer for: The Critical Path Method incorporates how many time estimates for activities__________________
Show answer

Answer: A. one time estimate

The standard Critical Path Method uses single-point deterministic time estimates for activities. Each activity is assigned one specific expected duration based on historical data or calculations. This deterministic appro...

Q3. Achieving an optimum project schedule implies that_______________?

Select your answer for: Achieving an optimum project schedule implies that_______________?
Show answer

Answer: B. lowest possible cost and shortest possible time for project

An optimum project schedule achieves the lowest possible cost and the shortest possible time for execution. Project crashing adds direct costs to reduce duration until indirect expenses and crashing costs balance perfect...

Q4. The industrial expediting function entails maintaining continuous oversight of__________________?

Select your answer for: The industrial expediting function entails maintaining continuous oversight of__________________?
Show answer

Answer: B. flow of material and in case of trouble locate source of trouble

Industrial expediting maintains continuous oversight of material flow to quickly locate and resolve operational bottlenecks. Expediters track component deliveries and production progress to prevent manufacturing delays b...

Q5. Urgent emergency rush orders can be processed and expedited most effectively within__________________?

Select your answer for: Urgent emergency rush orders can be processed and expedited most effectively within__________________?
Show answer

Answer: D. intermittent production

Intermittent production systems feature flexible layouts and general-purpose machinery. This operational flexibility allows job shops to handle custom or rush orders efficiently. Emergency orders can be scheduled into in...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test