Question no. 57959

Work sampling observations are systematically scheduled and recorded on the basis of_______________?

Select your answer for: Work sampling observations are systematically scheduled and recorded on the basis of_______________?
Show answer

Answer: C. table of random numbers

Explanation

Work sampling observations must be scheduled randomly to eliminate personal bias from the data. A table of random numbers ensures that every observation time has an equal chance of selection. Statistical validity relies heavily on random sampling techniques to accurately reflect true work activities. Work sampling is a statistical technique used to determine the proportion of time spent on various activities. Random timing prevents operators from altering their normal behavior when observers are scheduled to arrive. Industrial engineers use random number tables to generate unbiased observation schedules throughout the shift.

Plant managers use work sampling to evaluate machine utilization and identify sources of manufacturing downtime. This method is much more cost-effective than continuous time study for long-cycle assembly operations. Accurate activity ratios help facilities optimize staffing levels and improve overall operational productivity. Detailed calculations are used during data analysis rather than for scheduling the raw observation times. Convenience scheduling introduces severe human bias and invalidates the statistical accuracy of the study. Past experience does not provide the mathematical randomness required for valid work sampling schedules.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Which factory layout configuration is best aligned with custom job-order production__________________?

Select your answer for: Which factory layout configuration is best aligned with custom job-order production__________________?
Show answer

Answer: A. process layout

Custom job-order production relies on process layouts because similar functional machines are grouped together. This layout flexibility allows varied custom routing paths required for specialized low-volume manufacturing...

Q2. What organizational framework is typically preferred within the automotive manufacturing industry________________?

Select your answer for: What organizational framework is typically preferred within the automotive manufacturing industry________________?
Show answer

Answer: D. line and staff organisations

Line and staff organizations combine direct operational line authority with specialized advisory staff departments. Automotive manufacturing requires direct production lines combined with expert engineering, quality cont...

Q3. Which organizational structure proves most suitable for large integrated steel mills__________________?

Select your answer for: Which organizational structure proves most suitable for large integrated steel mills__________________?
Show answer

Answer: D. line, staff and functional organisations

Large integrated steel mills utilize a combination of line, staff, and functional organizational structures to manage complex operations. The massive scale of steel manufacturing requires specialized functional departmen...

Q4. Which of the options below qualifies as an example of a group incentive plan?

Select your answer for: Which of the options below qualifies as an example of a group incentive plan?
Show answer

Answer: C. Lincoln Plan

The Lincoln Incentive Plan is a well-known example of a group incentive scheme for productivity. It distributes bonuses based on the collective performance and profitability of the entire workforce. Group plans encourage...

Q5. Industrial work study is primarily concerned with_________________?

Select your answer for: Industrial work study is primarily concerned with_________________?
Show answer

Answer: A. improving present method and finding standard time

Industrial work study is primarily concerned with improving existing manufacturing methods and establishing reliable standard times. It achieves these goals through method study to eliminate waste and time study to measu...

Q6. The principal drawback associated with a line organization structure is_________________?

Select your answer for: The principal drawback associated with a line organization structure is_________________?
Show answer

Answer: D. all of the above

Line organization structures suffer from overburdened top executives, rigid structures, and potential communication bottlenecks. Because authority flows strictly downward in a single line, top leaders become bogged down...