Skip to main content
Sarkari MCQs Government Exam Question Bank
Menu
Question no. 57927

A positive slack value calculated on a PERT network signals that the project________________?

Select your answer for: A positive slack value calculated on a PERT network signals that the project________________?
Show answer

Answer: A. ahead of schedule

Explanation

A positive slack value calculated on a PERT network signals that the project or task is ahead of schedule. Slack represents the amount of extra time leeway available without delaying the overall project completion date. Positive float indicates that activities possess spare time buffers and do not restrict the critical path. Total float or slack is calculated as the difference between latest finish time and earliest finish time. Critical path activities maintain zero or negative slack, meaning any delay directly pushes out project completion. Project managers monitor slack values to reallocate resources from non-critical tasks to critical path bottlenecks.

Beyond schedule describes negative slack situations where projects are delayed relative to required deadlines. As per schedule typically describes zero slack baseline conditions or tasks right on target without extra float. Being on the critical path indicates zero slack rather than a positive slack time leeway value.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The total allowed time allocated for a work task equals the standard time plus___________________?

Select your answer for: The total allowed time allocated for a work task equals the standard time plus___________________?
Show answer

Answer: A. policy allowance

The total allowed time allocated for a work task equals the standard time plus policy allowance. Policy allowances are management-granted time additions included for specific organizational reasons. These extra percentag...

Q2. The Employees' Provident Funds Act applies broadly to________________?

Select your answer for: The Employees' Provident Funds Act applies broadly to________________?
Show answer

Answer: D. the industries notified by Government

The Employees' Provident Funds Act applies broadly to industries notified by government. Official government notifications legally mandate provident fund coverage for specific industrial sectors. Legislative frameworks a...

Q3. The earliest formalized method invented for industrial project planning was________________?

Select your answer for: The earliest formalized method invented for industrial project planning was________________?
Show answer

Answer: A. bar chart method

The bar chart method was pioneered by Henry Gantt in the early twentieth century. It established the first formalized graphical approach to industrial project planning. This visual scheduling tool laid the groundwork for...

Q4. The systematic methodology of value analysis can be successfully applied to____________________?

Select your answer for: The systematic methodology of value analysis can be successfully applied to____________________?
Show answer

Answer: E. any item

The systematic methodology of value analysis can be successfully applied to any item or component. Value analysis examines the functional requirements of a product to reduce costs without sacrificing quality. Any manufac...

Q5. The administrative technique for establishing and maintaining relative priorities among various project tasks is designated as___________________?

Select your answer for: The administrative technique for establishing and maintaining relative priorities among various project tasks is designated as___________________?
Show answer

Answer: B. critical ratio scheduling

Critical ratio scheduling is an administrative technique used to establish relative priorities. Project task priorities are dynamically updated using calculated critical ratio values. Managing competing tasks effectively...

Q6. Project scheduling provides management with crucial data concerning____________________?

Select your answer for: Project scheduling provides management with crucial data concerning____________________?
Show answer

Answer: A. when work should start and how much work should be completed during a certain period

Project scheduling provides management with crucial data regarding project timelines. It specifies exactly when work should start and how much work is expected. This enables managers to track progress across specific ope...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test