The administrative technique for establishing and maintaining relative priorities among various project tasks is designated as___________________?
Show answer Hide answer
Answer: B. critical ratio scheduling
Explanation
Critical ratio scheduling is an administrative technique used to establish relative priorities. Project task priorities are dynamically updated using calculated critical ratio values. Managing competing tasks effectively ensures critical deadlines are consistently met on time. Critical ratio is calculated by dividing time remaining until due date by work remaining. A critical ratio below one indicates that the job is running behind schedule. Production controllers use this numerical index to rank shop floor job priorities.
Job shop managers schedule daily machining operations using critical ratio priority rules. Manufacturing plants handling custom orders rely on critical ratios to expedite urgent work. Dynamic priority scheduling reduces order delivery delays in complex multi-product factories. Event flow scheduling technique is not the standard term used for priority ratios. Slotting technique for scheduling relates to warehouse space allocation rather than task priorities. Short interval scheduling manages short-term labor productivity rather than multi-task priority ratios.
- Subject
- Engineering
- Category
- Mechanical Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. A process layout format is most advantageously applied where______________?
Show answer Hide answer
Answer: C. few number of non-standardised units are to be produced
Process layouts group similar machines and functional operations together into dedicated departmental areas within the workshop. This functional grouping makes the layout ideal for producing small batches of customized o...
Q2. A positive slack value calculated on a PERT network signals that the project________________?
Show answer Hide answer
Answer: A. ahead of schedule
A positive slack value calculated on a PERT network signals that the project or task is ahead of schedule. Slack represents the amount of extra time leeway available without delaying the overall project completion date....
Q3. The statistical probability distribution governing activity durations in PERT follows__________________?
Show answer Hide answer
Answer: C. beta
PERT models activity duration uncertainty using the beta probability distribution curve. The beta distribution is selected because it accommodates single-mode, skewed, and bounded time estimates effectively. Calculating...
Q4. The specific time span by which an activity's completion can be delayed without postponing the start of successor tasks is termed_________________?
Show answer Hide answer
Answer: C. free float
Free float measures the exact time span an activity can be delayed without postponing the earliest start date of any successor task. This specific float calculation allows project schedulers to absorb minor operational d...
Q5. Executing a specific defined task within the CPM framework is referred to as______________________?
Show answer Hide answer
Answer: C. activity
Within the Critical Path Method framework, executing a specific defined task is referred to as an activity. Activities consume both time and tangible resources while transforming inputs into project deliverables. Network...
Q6. The simplex algorithm serves as the foundational mathematical method for__________________?
Show answer Hide answer
Answer: C. linear programming
The simplex algorithm is a standard iterative mathematical procedure used to solve linear programming optimization problems. Linear programming models maximize or minimize objective functions subject to linear constraint...