Which concept is best defined by “the degree of uncertainty that the product will meet its requirements and be fit for its intended use.”?
Show answer Hide answer
Answer: A. Performance risk
Explanation
Performance risk measures the uncertainty that a product will meet requirements and suit its intended use. It evaluates whether the software will deliver the required operational performance and functionality. High performance risk indicates potential failure in satisfying user expectations and system constraints. Software risk management identifies uncertainties that could negatively impact project outcomes. Performance risks often emerge when building complex systems with tight throughput requirements. Mitigating performance risk requires rigorous prototyping, testing, and continuous user feedback.
Real-time embedded systems face high performance risks regarding processing speed and memory limits. Project managers track performance risks to ensure software meets contractual quality standards. Evaluating performance risk early prevents costly redesign efforts late in the development cycle. Cost risk relates to the uncertainty of exceeding budget allocations during development. Support risk involves uncertainties regarding maintenance, documentation, and long-term product upkeep. Schedule risk measures the probability that a project will fail to meet established delivery deadlines.
- Subject
- Computer Science
- Category
- Software Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Which option fails to qualify as a project management objective ?
Show answer Hide answer
Answer: D. Avoiding customer complaints
Project management objectives focus on budgets, schedules, and team performance rather than avoiding complaints. Selecting option D correctly identifies the item that fails to qualify as a core management objective. Avoi...
Q2. Which procedure evaluates the costs and advantages associated with proposed modifications ?
Show answer Hide answer
Answer: A. Change management
Change management evaluates costs and benefits of proposed system modifications. It provides a structured process for approving or rejecting software changes. This procedure ensures that modifications align with project...
Q3. Which principle posits that work expands to consume the available timeframe ?
Show answer Hide answer
Answer: C. Parkinson’s Law
Parkinson’s Law posits that work expands to consume the available timeframe allocated for its completion. If a project is given too much time, tasks naturally stretch out to fill every available calendar day. Project man...
Q4. Which task is excluded from Software Configuration Management operations ?
Show answer Hide answer
Answer: B. Risk management
Risk management is a separate discipline, leaving it excluded from software configuration management operations. Selecting option B correctly identifies the activity not included within configuration management tasks. Co...
Q5. Which approach applies empirical formulas to forecast effort based on lines of code (LOC) or function points (FP) ?
Show answer Hide answer
Answer: D. Both FP-Based Estimation and COCOMO
Both FP-based estimation and COCOMO use empirical formulas for effort forecasting. They translate size metrics into predicted development hours and costs. These methods rely on historical data to build mathematical estim...
Q6. Which option fails to qualify as a risk management activity ?
Show answer Hide answer
Answer: B. Risk generation
Risk generation is not a standard risk management activity within software engineering frameworks. Standard risk management comprises identification, assessment, mitigation planning, and ongoing control. Projects natural...