Question no. 55902

If 6 men collaborating can finish 50 identical tasks in 4 hours, how many such tasks can 10 collaborating men finish in 6 hours?

Select your answer for: If 6 men collaborating can finish 50 identical tasks in 4 hours, how many such tasks can 10 collaborating men finish in 6 hours?
Show answer

Answer: C. 125

Explanation

Task completion rate depends on the product of workers and time expended. Dividing tasks by total man hours gives the productivity rate per worker hour. Scaling this rate for ten men working six hours yields one hundred twenty five tasks. Work rate problems assume uniform productivity among all collaborating individuals. Man hours quantify the total effort required to complete a specific project. Proportions allow scaling output when workforce and duration change proportionally.

Project managers estimate team workloads to schedule manufacturing deadlines effectively. Factory supervisors calculate production outputs based on available machinery and staff. Construction firms plan labor allocations to meet contractual completion targets. Option A assumes a lower productivity rate that contradicts standard scaling rules. Option B represents an incorrect proportional calculation for increased workforce duration. Option D underestimates output by failing to account for additional working hours.

Subject
Mathematics
Category
Mathematics
Topic
—
Difficulty
medium

Related questions

Q1. Given identical enclosed areas for a circle, square, or equilateral triangle, which shape exhibits the maximum perimeter_________?

Select your answer for: Given identical enclosed areas for a circle, square, or equilateral triangle, which shape exhibits the maximum perimeter_________?
Show answer

Answer: D. Both Triangle and Square

Among standard geometric shapes sharing an identical enclosed area, the circle yields the shortest perimeter. Both squares and equilateral triangles require larger perimeters to enclose the exact same surface area. Becau...

Q2. Vending an item at a 19% profit rather than a 12% profit yields an additional Rs. 105. What is the item's cost price?

Select your answer for: Vending an item at a 19% profit rather than a 12% profit yields an additional Rs. 105. What is the item's cost price?
Show answer

Answer: C. Rs. 1500

The difference between a 19 percent profit and a 12 percent profit is 7 percent. This 7 percent profit difference accounts for the additional Rs. 105 in selling price. Dividing 105 by 0.07 gives the total cost price of R...

Q3. If a man rows at 5 km/h in calm water and his speed against the current is 3.5 km/h, what is his rowing speed with the current__________?

Select your answer for: If a man rows at 5 km/h in calm water and his speed against the current is 3.5 km/h, what is his rowing speed with the current__________?
Show answer

Answer: C. 6.5 kmph

Subtracting the speed against the current from calm water speed reveals the stream velocity. Five kilometers per hour minus three point five kilometers per hour equals one point five. Adding this stream velocity back to...

Q4. If eggs are priced at $.06 each, what should a dozen eggs cost?

Select your answer for: If eggs are priced at $.06 each, what should a dozen eggs cost?
Show answer

Answer: C. $ .72

The cost of a single egg is given as six cents or zero point zero six dollars. A dozen items always consists of exactly twelve individual units according to standard counting definitions. Multiplying twelve eggs by zero...

Q5. If 28 men complete a project in 15 days, how many days will 21 men take to complete the same project___________?

Select your answer for: If 28 men complete a project in 15 days, how many days will 21 men take to complete the same project___________?
Show answer

Answer: D. 20 days

Total work required to complete a project is measured in man-days of effort. Multiplying 28 men by 15 days gives a total project workload of 420 man-days. Dividing 420 man-days by 21 men yields 20 days required to comple...

Q6. Given n(U)=60, n(A)= 35, n(B)=24, and n(AUB)’=10, determine the value of n(A∩B) ____________?

Select your answer for: Given n(U)=60, n(A)= 35, n(B)=24, and n(AUB)’=10, determine the value of n(A∩B) ____________?
Show answer

Answer: C. 9

Subtracting the external complement from the universal set size gives the union set cardinality. Sixty minus ten yields fifty elements present within the combined union set. Applying the inclusion-exclusion principle rev...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test