Compute the total count of bricks, sized 25 cm * 15 cm * 8 cm, needed to build a wall measuring 10 m * 4 m * 5 m, assuming 10% of the wall's volume is taken up by mortar?
Show answer Hide answer
Answer: C. 6000
Explanation
Calculating the total volume of the wall determines the overall spatial dimensions required. Subtracting the ten percent mortar volume leaves the net spatial volume occupied solely by bricks. Dividing the net brick volume by the individual brick size yields the total count of six thousand. Masonry calculations account for mortar joints by deducting a percentage from total wall volume. Volume is computed as the product of length, width, and height using consistent units. Dividing total material volume by single unit volume determines the required quantity of items.
Construction estimators calculate brick and mortar requirements to budget building materials accurately. Architectural planning uses volumetric analysis to ensure structural integrity and material efficiency. Civil engineering projects rely on precise material counts to prevent construction site shortages. Option A underestimates the brick count by failing to account for the full wall volume. Option B represents an intermediate calculation that ignores the specific mortar deduction percentage. Option D overstates the required brick count by miscalculating the net volume ratio.
- Subject
- Mathematics
- Category
- Mathematics
- Topic
- —
- Difficulty
- medium
Related questions
Q1. By trading an umbrella for Rs. 300, a merchant secures a 20% gain. During a clearance event, he offers a 10% markdown on the marked price. What is his percentage gain during this event:________?
Show answer Hide answer
Answer: C. 8
Selling for three hundred with a twenty percent gain establishes a cost price of two hundred fifty. Applying a ten percent markdown to the marked price of three hundred gives a new price of two hundred seventy. Calculati...
Q2. What are the coordinates of the origin:___________?
Show answer Hide answer
Answer: C. (0,0)
The origin on any standard Cartesian coordinate system represents the central reference intersection point. Both the horizontal axis and vertical axis meet precisely at zero units of measurement. Standard mathematical no...
Q3. C requires 6 days to finish half of a task, while D takes 5 days to complete 1/3rd of the same task. Working in alternating turns with C taking the initial 4 days, how many days will D need to finish the remaining work independently?
Show answer Hide answer
Answer: A. 10 days
C completes the whole task in 12 days and D completes it in 15 days. In the initial 4 days of alternating work, C completes one-third of the total task. D requires 10 independent days to finish the remaining two-thirds o...
Q4. Calculate the arithmetic mean of 1, 2, 3, 4, 5.
Show answer Hide answer
Answer: C. 3
Summing the sequence values one, two, three, four, and five gives a total of fifteen. Dividing the total sum of fifteen by the element count of five calculates the mean. The resulting arithmetic mean calculation precisel...
Q5. An investment grows by 1/8th of its value annually. Starting with a present principal of Rs.64000, what will its value be after two years?
Show answer Hide answer
Answer: A. Rs.81000
An annual growth of one eighth increases the investment value to nine eighths annually. Multiplying the initial principal of sixty four thousand by nine eighths twice accounts for years. Completing this compound growth c...
Q6. Bilal finishes a task in 15 days and Jalal in 12 days. If they collaborate for 4 days, what fraction of the work remains unfinished________?
Show answer Hide answer
Answer: C. 2/5
Bilal works at a daily rate of one-fifteenth and Jalal at one-twelfth. Their combined collaborative daily rate totals nine-sixtieths or three-twentieths. Working 4 days completes twelve-twentieths, leaving an unfinished...