A, B, and C complete a task in 8, 14, and 16 days. A works 2 days, B finishes 2/3 of the remainder, and C completes the rest. Total days taken?
Show answer Hide answer
Answer: A. 13
Explanation
Worker A completes one quarter of the total project in the initial two days worked. Worker B finishes half of the total project during the assigned remainder phase. Worker C completes the final quarter of work, bringing total accumulated days to thirteen. Work rate problems assume individuals perform tasks at steady, uninterrupted daily speeds. Fractions of work completed by individuals must sum up to a whole project unit. Sequential task scheduling requires calculating remaining workloads after each participant finishes.
Project management relies on calculating individual work rates to establish realistic construction deadlines. Construction planning requires coordinating multiple laborers with differing productivity levels. Understanding fractional completion rates helps managers reallocate tasks when delays occur. Option B leaves a portion of the project incomplete when calculating the final schedule. Option C overestimates the time required for finishing the remaining workload segments. Option D provides an excessive duration that contradicts the combined work rate totals.
- Subject
- Mathematics
- Category
- Mathematics
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Three pipes A, B, and C fill a tank in eight hours. With pipe A having twice the rate of B, and B twice that of C, how long will pipe B take alone?
Show answer Hide answer
Answer: B. 28 hours
Expressing individual pipe rates relative to variable x establishes a combined rate equation. Combining the rates of pipes A, B, and C gives a total proportional working rate. Isolating pipe B allows calculation of its s...
Q2. A two-digit number has digits with a product of 8. Adding 18 reverses the digits. Find the number :_________?
Show answer Hide answer
Answer: B. 24
The correct two-digit number is identified by testing candidates whose individual digits multiply together to equal eight. For the number twenty-four, multiplying the digits two and four yields the required product of ei...
Q3. After pouring 38 liters of petrol, the tank was still 5% empty. How much more petrol is needed to fill it?
Show answer Hide answer
Answer: D. 2 liters
Recognizing that thirty-eight liters represents ninety-five percent capacity establishes the total volume equation. Calculating the full one hundred percent capacity reveals the maximum holding limit of the tank. Multipl...
Q4. An item costs Rs.912 after a 24% price reduction. What was its original cost?
Show answer Hide answer
Answer: C. 1200
A 24 percent price reduction means the final cost represents 76 percent of original. Dividing the reduced price by 0.76 calculates the initial pre-reduction cost. Dividing 912 by 0.76 results in the correct original cost...
Q5. Ameen invests Rs. 70,000 to start a business, followed by Rahim with Rs. 1,05,000 after six months, and Sameer with Rs. 1.4 lakhs six months later. In what ratio is the 3-year profit distributed among them?
Show answer Hide answer
Answer: B. 12:15:16
The correct profit distribution ratio is found by multiplying each investor's capital by the number of months it remained active. Ameen's investment runs for the full thirty-six months, while Rahim and Sameer invest for...
Q6. A trader marks a TV 30% above cost and offers a 10% discount, gaining Rs.340. Find the cost price of the TV.
Show answer Hide answer
Answer: B. Rs.2000
Applying the markup and discount percentages to a base cost of one hundred determines the profit percentage. Equating the resulting profit percentage to the given monetary value establishes a direct proportion. Solving t...