15 workers construct a 500m wall in 30 days. How many days will 30 workers require to build a 1.2 km wall?
Show answer Hide answer
Answer: D. 36 days
Explanation
Using proportional man-day and wall-length calculations determines that 30 workers require 36 days. The total work required increases proportionally with the length of the wall being constructed. Doubling the workforce halves the required time, adjusted further for the increased wall length. Work problems are solved using the formula relating workers, days, and output units. Fifteen workers take 30 days for 500 meters, representing 450 total worker-days. A 1.2 kilometer wall requires 1200 meters, scaling the total required labor effort accordingly.
Construction project managers use proportional labor calculations for scheduling and budgeting. Accurate resource estimation prevents costly delays on large infrastructure development projects. Understanding worker-day ratios is fundamental for operational efficiency in contracting. Option a overestimates the required days by incorrectly scaling the labor productivity ratio. Option b underestimates the time needed to construct the longer 1.2 km wall. Option c represents an intermediate calculation error in the proportionality formula.
- Subject
- Mathematics
- Category
- Mathematics
- Topic
- —
- Difficulty
- medium
Related questions
Q1. 10 books are arranged randomly on a bookshelf. What is the probability that a specific book pair remains adjacent_________?
Show answer Hide answer
Answer: C. 1/5
The probability that a specific book pair remains adjacent in a random arrangement is 1/5. Treating the adjacent book pair as a single combined unit reduces the arrangement objects to nine. Calculating favorable permutat...
Q2. (1.9 * 0.021) / (0.095 * 0.105) = ______?
Show answer Hide answer
Answer: C. 4
Simplifying the decimal fraction expression results in 4. Converting decimals to fractions helps cancel common factors across the numerator and denominator. Evaluating the simplified terms leaves a clean integer result e...
Q3. 16.66% of 33.33% of 66.66% of ? = 30
Show answer Hide answer
Answer: C. 810
Solving the nested percentage equation backwards determines the unknown value to be eight hundred ten. Converting percentages to fractions allows step-by-step reverse calculation of the unknown variable. Multiplying thir...
Q4. Calculate 15% of 195 + 14% of 205 = _______?
Show answer Hide answer
Answer: C. 58
Calculating 15% of 195 and 14% of 205 and summing them gives 58. Fifteen percent of 195 evaluates to 29.25 in decimal arithmetic notation. Fourteen percent of 205 evaluates to 28.70, and their sum equals exactly 58. Perc...
Q5. Find the value of 2003 * 2004 – 2001 * 2002 = _________?
Show answer Hide answer
Answer: B. 8010
Expanding and simplifying the product difference yields the exact result of eight thousand ten. Algebraic substitution allows quick calculation without multiplying large four-digit numbers directly. Setting variables for...
Q6. Grazing a pasture takes 12 days for 18 head of cattle. If 6 cattle are used, how many days (x) will it take them to graze 3 equivalent pastures?
Show answer Hide answer
Answer: D. 108
Applying proportional cattle-day-pasture formulas determines that grazing three equivalent pastures takes 108 days. Reducing the number of cattle increases the required grazing duration proportionally for a single pastur...