Question no. 57945

The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?

Select your answer for: The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
Show answer

Answer: E. dummy

Explanation

A dummy activity acts as a logical link indicating that a successor task cannot start until a predecessor completes. Network diagrams use these artificial links to maintain proper precedence relationships without consuming any actual project time. Engineers insert dummy tasks specifically to resolve logical conflicts when drawing complex arrow diagramming method schedules. Dummy activities are represented by dashed arrows in traditional project management network diagrams. They consume zero time and zero resources in the overall critical path method calculation. The primary purpose is to preserve correct logical sequencing and dependency rules between project tasks.

Project managers rely on network diagrams to schedule large construction and manufacturing projects efficiently. Understanding dependencies helps prevent costly delays by identifying which tasks must finish first. Software tools automate these logical relationships, but human planners must understand the underlying principles. Events represent specific points in time marking the start or completion of designated project activities. Free float indicates the amount of time a task can be delayed without delaying any subsequent activities. Constraints are external limitations or restrictions imposed on project schedules rather than internal logical links.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The operational time that yields the absolute minimum direct cost for an activity is recognized as________________?

Select your answer for: The operational time that yields the absolute minimum direct cost for an activity is recognized as________________?
Show answer

Answer: B. slow time

Crash time represents the absolute shortest duration possible to complete a given activity successfully. Slow time or normal time settings carry different cost implications for project managers. Accelerating an activity...

Q2. In methods-time measurement, the acronym TMU expands to__________________?

Select your answer for: In methods-time measurement, the acronym TMU expands to__________________?
Show answer

Answer: B. time measurement unit

In methods-time measurement, the acronym TMU officially expands to time measurement unit. Time measurement units provide a standardized numerical scale for evaluating manual motions. Conversion factors link these special...

Q3. Value engineering is primarily directed toward discovering________________?

Select your answer for: Value engineering is primarily directed toward discovering________________?
Show answer

Answer: C. major function of the item and accomplishing the same at least cost without change in quality

Value engineering focuses on identifying an item primary function and achieving it at lowest cost. Cost reduction is accomplished without compromising the required quality, reliability, or performance standards. The meth...

Q4. An incentive plan where a job completion time is set and a bonus is paid based on the exact percentage of time saved is designated as_________________?

Select your answer for: An incentive plan where a job completion time is set and a bonus is paid based on the exact percentage of time saved is designated as_________________?
Show answer

Answer: E. Rowan Plan

The Rowan Plan specifically calculates worker bonuses based on the exact percentage of time saved. Workers under this scheme receive additional pay proportional to the fraction of standard time saved. This method prevent...

Q5. Within the context of value engineering, the term 'value' denotes_______________?

Select your answer for: Within the context of value engineering, the term 'value' denotes_______________?
Show answer

Answer: C. utility of the product

Value engineering defines value strictly as the utility or functional worth of products. Product utility reflects how effectively an item satisfies specific customer functional requirements. Maximizing functional utility...

Q6. Examine the choices and identify the odd one out_______________?

Select your answer for: Examine the choices and identify the odd one out_______________?
Show answer

Answer: D. Galileo

Galileo was an Italian astronomer and physicist, making him completely unrelated to management theory. The other listed individuals are renowned pioneers in the field of business and organizational management. Historical...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test