Question no. 57947

An incentive plan where a job completion time is set and a bonus is paid based on the exact percentage of time saved is designated as_________________?

Select your answer for: An incentive plan where a job completion time is set and a bonus is paid based on the exact percentage of time saved is designated as_________________?
Show answer

Answer: E. Rowan Plan

Explanation

The Rowan Plan specifically calculates worker bonuses based on the exact percentage of time saved. Workers under this scheme receive additional pay proportional to the fraction of standard time saved. This method prevents excessive bonus payouts while still rewarding workers for high operational efficiency. Wage incentive plans aim to motivate workers to increase productivity and complete jobs faster. James Rowan introduced this specific premium system in the early twentieth century for manufacturing shops. The bonus formula multiplies the time taken by the ratio of time saved to standard time.

Industrial engineers implement such incentive structures to balance labor productivity with manufacturing cost controls. Fair wage plans improve worker morale and reduce turnover in labor-intensive industrial production environments. Payroll departments rely on precise time study data to calculate accurate incentive bonuses weekly. The Halsey Premium Plan shares only a fixed percentage, usually fifty percent, of the time saved. The Taylor Plan utilizes differential piece rates based entirely on whether workers meet standard output quotas. The Bedaux Plan measures work in standard rating units called points rather than direct time percentages.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Value engineering is primarily directed toward discovering________________?

Select your answer for: Value engineering is primarily directed toward discovering________________?
Show answer

Answer: C. major function of the item and accomplishing the same at least cost without change in quality

Value engineering focuses on identifying an item primary function and achieving it at lowest cost. Cost reduction is accomplished without compromising the required quality, reliability, or performance standards. The meth...

Q2. Material wastage within the storeroom is accounted for through which evaluation method when issuing materials_______________?

Select your answer for: Material wastage within the storeroom is accounted for through which evaluation method when issuing materials_______________?
Show answer

Answer: A. inflated system

An inflated pricing system accounts for inevitable storeroom material wastage by adding a calculated percentage surcharge to issue costs. This accounting method ensures that the cost of minor material shrinkage, handling...

Q3. The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?

Select your answer for: The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
Show answer

Answer: E. dummy

A dummy activity acts as a logical link indicating that a successor task cannot start until a predecessor completes. Network diagrams use these artificial links to maintain proper precedence relationships without consumi...

Q4. Examine the choices and identify the odd one out_______________?

Select your answer for: Examine the choices and identify the odd one out_______________?
Show answer

Answer: D. Galileo

Galileo was an Italian astronomer and physicist, making him completely unrelated to management theory. The other listed individuals are renowned pioneers in the field of business and organizational management. Historical...

Q5. Within work study charting conventions, what does the symbol 'D' signify ___________________?

Select your answer for: Within work study charting conventions, what does the symbol 'D' signify ___________________?
Show answer

Answer: C. delay/temporary storage

Work study charting conventions utilize standardized symbols to document manufacturing processes clearly and consistently. The letter D specifically represents a delay or temporary storage interval where a workpiece wait...

Q6. What operational action does the symbol 'V' represent in work study symbology________________?

Select your answer for: What operational action does the symbol 'V' represent in work study symbology________________?
Show answer

Answer: D. permanent storage

In standard work study flow process charts, the symbol V represents permanent storage of materials or parts. Work study analysts use standardized geometric symbols to document every single action in a manufacturing proce...