Select the false statement regarding the applications of time study_________________?
Show answer Hide answer
Answer: A. determine overhead expenses
Explanation
Time study techniques measure direct labor work durations to establish standard production times. Overhead expenses represent general business costs determined through formal financial accounting. Therefore, time study is not used to directly determine general overhead expenses. Industrial engineers use stopwatch time study or predetermined motion time systems for work measurement. Standard times calculated from studies form the basis for production planning and wage incentives. Overhead costs include facility rent, utilities, and administrative expenses distributed across production.
Manufacturing plants rely on accurate time studies to improve labor efficiency and line balancing. Cost accountants use standard labor times combined with overhead rates to calculate product costs. Understanding work measurement helps eliminate wasted motion and enhances manufacturing productivity. Providing a basis for piece prices and incentive wages is a primary application of time studies. Determining standard labor costs for products directly depends on accurate time study data. Evaluating operator capability to handle multiple machines relies on workplace time measurement.
- Subject
- Engineering
- Category
- Mechanical Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Break-even analysis can be practically applied for evaluating__________________?
Show answer Hide answer
Answer: A. short run analysis
Break-even analysis evaluates cost-volume-profit relationships under fixed plant capacity constraints. Fixed capacity limits and constant cost structures restrict this tool primarily to short-run analysis. Long-run busin...
Q2. Under the MAPI replacement formula guidelines, an aging machine should be superseded by a new model when_____________?
Show answer Hide answer
Answer: A. CAM < DAM
Under MAPI replacement formula guidelines an aging machine is superseded when adverse minimum average is lower than next-year operating inferiority. The challenger machine minimum average cost represents its annualized c...
Q3. Real or practical fluids are characterized by___________________?
Show answer Hide answer
Answer: D. possess all the above properties
Real fluids possess viscosity, surface tension, and compressibility, unlike idealized theoretical fluids. Every practical fluid exhibits internal frictional resistance to shear flow, quantified as dynamic or kinematic vi...
Q4. The Critical Path Method incorporates how many time estimates for activities__________________
Show answer Hide answer
Answer: A. one time estimate
The standard Critical Path Method uses single-point deterministic time estimates for activities. Each activity is assigned one specific expected duration based on historical data or calculations. This deterministic appro...
Q5. Achieving an optimum project schedule implies that_______________?
Show answer Hide answer
Answer: B. lowest possible cost and shortest possible time for project
An optimum project schedule achieves the lowest possible cost and the shortest possible time for execution. Project crashing adds direct costs to reduce duration until indirect expenses and crashing costs balance perfect...
Q6. The activity slack or float associated with any node on a PERT/CPM chart is shown by__________________?
Show answer Hide answer
Answer: D. anyone of the above
Activity float or slack can be calculated using various combinations of latest and earliest start/finish times. Total float represents the amount of time an activity can be delayed without delaying the overall project co...