Select the correct statement: A dummy activity in a PERT/CPM network indicates that it_________________?

Select your answer for: Select the correct statement: A dummy activity in a PERT/CPM network indicates that it_________________?
Show answer

Answer: C. consumes neither time nor resources

Explanation

A dummy activity is represented by a dashed arrow in PERT and CPM network diagrams. It is used solely to maintain correct logical precedence relationships between events. Because it is a conceptual link, it consumes neither time nor physical resources. Network rules dictate that two events cannot share the same start and finish node numbers. Dummy arrows resolve naming conflicts and clarify complex network dependency logic. Zero duration and zero resource consumption distinguish dummy activities from real work tasks.

Project schedulers insert dummy activities when configuring complex logic in software models. Understanding dummy tasks prevents errors in calculating earliest and latest event times. Network optimization relies on accurate logical representations without artificial resource inflation. Option A is wrong because dummy activities have zero duration and consume no time. Option B is incorrect because they require no physical resources whatsoever. Option D is wrong because a dangling event represents an unconnected network error.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. PERT project analysis is fundamentally built upon____________________?

Select your answer for: PERT project analysis is fundamentally built upon____________________?
Show answer

Answer: D. all of the above

PERT project analysis is fundamentally built upon optimistic time, pessimistic time, and most likely time estimates. Combining these three distinct statistical estimates allows PERT models to calculate expected task dura...

Q2. Statistical quality control (SQC) methodologies rely heavily on the underlying principles of___________________?

Select your answer for: Statistical quality control (SQC) methodologies rely heavily on the underlying principles of___________________?
Show answer

Answer: C. probability

Statistical quality control methods are built upon the foundational mathematical principles of probability and statistics. Analyzing manufacturing process variation requires applying probability distributions and statist...

Q3. Standard time for an operation is formally defined as ____________________?

Select your answer for: Standard time for an operation is formally defined as ____________________?
Show answer

Answer: A. normal time + allowances

Standard time for an operation is formally defined as normal time plus appropriate allowances. Normal time measures the adjusted pace of a worker executing tasks without accounting for fatigue. Adding allowances for pers...

Q4. A string diagram analytical tool is employed for_________________?

Select your answer for: A string diagram analytical tool is employed for_________________?
Show answer

Answer: D. all of the above

A string diagram analytical tool is employed for analyzing complex layouts, group work arrangements, and worker movement paths. Placing pins on a scale layout and running continuous string tracks travel routes and conges...

Q5. The designated appellate authority for handling industrial disputes is________________?

Select your answer for: The designated appellate authority for handling industrial disputes is________________?
Show answer

Answer: C. high court/supreme court

High courts and the Supreme Court serve as the ultimate appellate judicial authorities for resolving complex industrial disputes. Constitutional courts review industrial tribunal decisions on points of law and jurisdicti...

Q6. String diagrams are specifically utilized under conditions where__________________?

Select your answer for: String diagrams are specifically utilized under conditions where__________________?
Show answer

Answer: A. team of workers is working at a place

String diagrams are specifically utilized under conditions where a team of workers is working in an area. Pins and colored threads map out movement pathways on a scaled floor plan to analyze travel efficiency. This visua...