Skip to main content
Sarkari MCQs Government Exam Question Bank
Menu
Question no. 57887

PERT and CPM project management techniques are applicable to which types of activities____________________?

Select your answer for: PERT and CPM project management techniques are applicable to which types of activities____________________?
Show answer

Answer: E. all of the above

Explanation

PERT and CPM project management techniques are applicable to diverse once-through and repetitive activities. Network scheduling models handle complex workflows across construction, maintenance, and research fields. These versatile tools track task dependencies regardless of whether the project is technical or administrative. PERT was developed for uncertainty-laden research projects while CPM handles deterministic construction tasks. Both techniques rely on network diagrams to identify critical paths and calculate project durations. Activities are broken down into discrete tasks with defined predecessors, successors, and time estimates.

Project managers across all industries rely on network techniques to control budgets and delivery schedules. Research and development projects benefit from probabilistic time estimates used in PERT network analysis. Construction planning uses CPM to optimize resource allocation and minimize costly project delays. Restricting PERT and CPM only to once-through projects ignores their widespread use in maintenance. Claiming they apply solely to research and development overlooks their massive role in construction. Limiting them to non-technical jobs ignores their heavy engineering and software development origins.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Job evaluation is a systematic method for ascertaining the________________?

Select your answer for: Job evaluation is a systematic method for ascertaining the________________?
Show answer

Answer: A. relative worth of jobs

Job evaluation is a formal administrative procedure used within human resources management. Its primary purpose is ascertaining the relative worth of different jobs within an organization. It evaluates job content rather...

Q2. In which of the following factory layout configurations is line balancing strictly required_______________?

Select your answer for: In which of the following factory layout configurations is line balancing strictly required_______________?
Show answer

Answer: B. product layout

Product layouts feature machines arranged in a strict sequential order matching the manufacturing steps of a specific product. Line balancing is strictly required in this configuration to ensure that every workstation op...

Q3. A circular node symbol (O) on a PERT/CPM network diagram represents____________________?

Select your answer for: A circular node symbol (O) on a PERT/CPM network diagram represents____________________?
Show answer

Answer: A. an ordinary event

In standard PERT and CPM network notation, circular nodes represent ordinary project events. An event node marks a specific instant in time representing the start or completion of project activities. Drawing circular sym...

Q4. Identify the incorrect statement regarding critical ratio job scheduling____________________?

Select your answer for: Identify the incorrect statement regarding critical ratio job scheduling____________________?
Show answer

Answer: E. none of the above

Critical ratio job scheduling calculates priorities based on remaining time and work. It establishes relative priorities, determines activity status, and adapts dynamically. Because all listed statements are correct, non...

Q5. Spot the erroneous statement concerning the practical benefits of work sampling_________________?

Select your answer for: Spot the erroneous statement concerning the practical benefits of work sampling_________________?
Show answer

Answer: A. permits a fine breakdown of activities and delays

Work sampling involves taking random instantaneous observations and is entirely unsuited for capturing fine breakdowns of minute activities or delays. Continuous time study using stopwatches is the correct methodological...

Q6. Pessimistic time estimate in network planning is defined as___________________?

Select your answer for: Pessimistic time estimate in network planning is defined as___________________?
Show answer

Answer: A. the maximum time which an activity might require

The pessimistic time estimate represents the maximum possible duration an activity might require under adverse conditions. Project planners use this value in PERT analysis to account for unexpected delays, equipment fail...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test