Examine the following statements and select the correct one?
Show answer Hide answer
Answer: E. none of the above
Explanation
Program Evaluation and Review Technique is specifically an event-oriented project management tool. Critical Path Method focuses primarily on activity durations and scheduling pathways. Since standard comparative statements mixing these definitions correctly are absent from choices A through D, none are correct. PERT uses probabilistic time estimates focused on specific project milestones or events. CPM uses deterministic time estimates focused on continuous work activities and completion paths. Project managers select these network techniques based on task uncertainty and scheduling needs.
Complex engineering projects rely on network scheduling methods to track progress and deadlines. Understanding whether a method is event or activity oriented helps planners apply correct tools. Project management software integrates both PERT and CPM principles for comprehensive planning. Stating PERT is event oriented is true in general project management theory, but option E correctly overrides. Claiming PERT is not event oriented contradicts standard project management definitions. CPM can be activity oriented, but standard definitions make the listed comparative statements incorrect.
- Subject
- Engineering
- Category
- Mechanical Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. The operation of a McLeod gauge for measuring very low vacuum pressures relies upon the physical principle of_________________?
Show answer Hide answer
Answer: B. Boyle’s law
A McLeod gauge measures high vacuum pressures by trapping and compressing a known volume of gas. The compression process follows Boyle law relating absolute pressure and gas volume inversely. Measuring the compressed gas...
Q2. Once a nuclear reactor achieves criticality, the net generation rate of neutrons_________________?
Show answer Hide answer
Answer: C. exactly balanced by the loss of neutrons through leakage
Once a reactor achieves criticality the net generation rate of neutrons is balanced by leakage and absorption. This exact equilibrium maintains a steady neutron population sustaining continuous power without surging. Pro...
Q3. The moderating material most commonly selected for nuclear reactors is___________________?
Show answer Hide answer
Answer: E. graphite
Graphite is widely used as a high-purity moderator due to its excellent moderating ratio and low neutron capture cross-section. Carbon atoms in high-density graphite effectively slow down fast fission neutrons through el...
Q4. Identify the incorrect assertion from the options below?
Show answer Hide answer
Answer: D. the arrows are drawn (to scale from) left to right
Project network arrows represent individual tasks but their physical lengths are not drawn to scale. Activity durations are indicated numerically alongside arrows rather than proportional to drawing lengths. Therefore dr...
Q5. Spot the incorrect statement concerning engine supercharging __________________?
Show answer Hide answer
Answer: D. supercharging results in fuel economy
Supercharging increases air density and fuel mass inside engine cylinders but generally increases overall fuel consumption. Forcing more air and fuel into combustion chambers produces higher power output rather than dire...
Q6. Select the false statement from the list provided?
Show answer Hide answer
Answer: A. aluminium in steel results in excessive grain growth
Aluminum added to molten steel acts primarily as an effective deoxidizer and grain refiner. Rather than causing excessive grain growth, aluminum nitride precipitates restrict austenitic grain expansion. Therefore, claimi...