A product layout configuration is specifically deployed for____________________?
Show answer Hide answer
Answer: B. continuous production
Explanation
A product layout configuration is specifically deployed for high-volume continuous or mass production. Machines and workstations are arranged in a sequential line matching the exact fabrication steps required. This dedicated flow minimizes material handling times and maximizes output rates for standardized goods. Product layouts contrast with process layouts where similar machines are grouped together in departments. Continuous production facilities operate twenty-four hours a day manufacturing uniform commodity items. Line balancing ensures that every workstation along a product layout operates at a synchronized speed.
Automobile assembly plants utilize product layouts to manufacture thousands of identical vehicles efficiently. High capital investment in dedicated machinery requires steady mass demand to justify product layouts. Any equipment breakdown along a product layout can halt the entire continuous manufacturing line. Batch production typically utilizes process layouts rather than dedicated linear product layouts. Effective utilization of machines is a general manufacturing goal rather than the definition of layout types. Claiming all of the above is wrong because product layouts are unsuited for batch or job production.
- Subject
- Engineering
- Category
- Mechanical Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Identify the incorrect statement regarding critical ratio job scheduling____________________?
Show answer Hide answer
Answer: E. none of the above
Critical ratio job scheduling calculates priorities based on remaining time and work. It establishes relative priorities, determines activity status, and adapts dynamically. Because all listed statements are correct, non...
Q2. Spot the erroneous statement concerning the practical benefits of work sampling_________________?
Show answer Hide answer
Answer: A. permits a fine breakdown of activities and delays
Work sampling involves taking random instantaneous observations and is entirely unsuited for capturing fine breakdowns of minute activities or delays. Continuous time study using stopwatches is the correct methodological...
Q3. Pessimistic time estimate in network planning is defined as___________________?
Show answer Hide answer
Answer: A. the maximum time which an activity might require
The pessimistic time estimate represents the maximum possible duration an activity might require under adverse conditions. Project planners use this value in PERT analysis to account for unexpected delays, equipment fail...
Q4. What are the primary operational limitations or discrepancies of traditional bar charts________________?
Show answer Hide answer
Answer: E. all of the above
Traditional bar charts fail to display complex interdependencies between project tasks clearly. They struggle to predict how delays in one activity impact the final completion date. Consequently, all listed operational l...
Q5. PERT is an acronym representing___________________?
Show answer Hide answer
Answer: E. all of the above
Program Evaluation and Review Technique serves as an event-oriented analytical framework designed for managing complex industrial projects. The methodology relies on three distinct time estimates for every activity to ac...
Q6. Queuing theory is a mathematical approach dealing with problems of________________?
Show answer Hide answer
Answer: B. reducing the waiting time or idle Jajme
Queuing theory is a mathematical approach dealing with problems of reducing waiting times and idle service resources. Probability models analyze customer arrival rates and service rates to optimize queue lengths and wait...