Skip to main content
Sarkari MCQs Government Exam Question Bank
Menu
Question no. 57852

What instrument is used to measure pressures around the 10⁻⁶ torr range__________________?

Select your answer for: What instrument is used to measure pressures around the 10⁻⁶ torr range__________________?
Show answer

Answer: D. ionisastion gauge

Explanation

Ionization gauges operate by ionizing gas molecules inside the vacuum chamber and measuring the resulting electrical current. This specific electrical current correlates directly with extremely low gas densities found in high vacuum environments down to 10⁻⁶ torr. Other mechanical gauges lack the necessary sensitivity to detect the minute gas pressures present in deep vacuum systems. A torr is a unit of pressure defined as exactly 1/760 of a standard atmosphere or one millimeter of mercury. High vacuum research and semiconductor manufacturing frequently require specialized instrumentation capable of measuring extremely rarefied gaseous environments. Hot cathode ionization gauges utilize a heated filament to emit electrons that collide with and ionize residual gas molecules.

Bourdon tube pressure gauges utilize elastic metal tubes that straighten under pressure, making them completely useless for measuring deep vacuums. Pirani gauges measure thermal conductivity of gases and are typically limited to medium vacuum ranges rather than extreme high vacuums. McLeod gauges compress a known volume of gas to measure pressure, but they are cumbersome and largely unsuitable for continuous electronic monitoring.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. The foundational analytical tool utilized in work study is __________________?

Select your answer for: The foundational analytical tool utilized in work study is __________________?
Show answer

Answer: D. stop watch

Work study relies on direct observation using a stopwatch as the fundamental tool for conducting time studies. Industrial engineers measure worker performance and cycle times accurately by timing operations directly with...

Q2. A Gantt chart supplies management with information concerning the________________?

Select your answer for: A Gantt chart supplies management with information concerning the________________?
Show answer

Answer: C. production schedule

A Gantt chart supplies management with clear visual information concerning the active production schedule. Horizontal bars represent task durations allowing managers to track progress against planned timelines easily. Th...

Q3. The critical path on a network chart is established by connecting sequential events possessing____________________?

Select your answer for: The critical path on a network chart is established by connecting sequential events possessing____________________?
Show answer

Answer: B. minimum slack

The critical path consists of a sequence of connected events and activities having the minimum total slack. Activities on the critical path determine the absolute minimum duration required to complete the entire project....

Q4. In micromotion analysis, a therblig elemental motion is described by_______________?

Select your answer for: In micromotion analysis, a therblig elemental motion is described by_______________?
Show answer

Answer: E. standard symbol and colour

Micromotion analysis uses therbligs, which are elemental motions represented by standard symbols and distinct colors. Each fundamental hand motion is categorized using a specific graphical symbol and a designated color c...

Q5. If TL designates the latest allowable time for an event occurrence, the total activity slack (s) is calculated as__________________?

Select your answer for: If TL designates the latest allowable time for an event occurrence, the total activity slack (s) is calculated as__________________?
Show answer

Answer: D. all of the above

Total activity slack can be computed using various standard differences between latest allowable and earliest times. Activity slack measures how much an operation can be delayed without extending the total project durati...

Q6. A Critical Path Network assists engineering professionals by_________________?

Select your answer for: A Critical Path Network assists engineering professionals by_________________?
Show answer

Answer: D. all of the above

Managers focus attention on critical activities to prevent overall project delays. Resources are dynamically reallocated from noncritical tasks to critical path items. Engineers stay extremely cautious regarding critical...