Rated lifting capacities for crawler-mounted and pneumatic-tired cranes, expressed as a percentage of tipping load at a given radius, are respectively_________________?

Select your answer for: Rated lifting capacities for crawler-mounted and pneumatic-tired cranes, expressed as a percentage of tipping load at a given radius, are respectively_________________?
Show answer

Answer: D. 75 and 83

Explanation

Rated lifting capacities are regulated as specific percentages of the crane tipping load. Crawler-mounted cranes use seventy-five percent due to crawler stability characteristics. Pneumatic-tired cranes use eighty-three percent because outriggers provide enhanced stabilization. Crane stability is governed by overturning moments balanced against machine weight and outriggers. Tipping load represents the weight that causes the crane to tip over at a given radius. Safety margins protect against dynamic wind loads and sudden load swings during lifting.

Rigging engineers consult crane load charts to ensure safe lifts on construction sites. Crawler cranes operate without outriggers in motion, requiring conservative capacity ratings. Pneumatic-tired cranes deploy outriggers to increase stability and lift heavier loads safely. Option A reverses the required capacity percentages for crawler and pneumatic-tired cranes. Option B provides incorrect percentage figures that do not match standard crane regulations. Option C lists inaccurate safety factor percentages for mobile crane stability ratings.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. What represents a primary limitation of conventional bar charts?

Select your answer for: What represents a primary limitation of conventional bar charts?
Show answer

Answer: D. all of the above

Conventional bar charts struggle to display task interdependencies clearly across complex schedules. Bar charts lack mechanisms to represent project uncertainties and probabilistic duration estimates. Tracking dynamic pr...

Q2. The managerial procedure of incorporating modifications and rescheduling a project is termed_______________?

Select your answer for: The managerial procedure of incorporating modifications and rescheduling a project is termed_______________?
Show answer

Answer: C. updating

Updating is the formal managerial procedure of incorporating project modifications and rescheduling. This process reflects actual site progress and adjusts remaining task timelines accordingly. Regular updating ensures p...

Q3. Which of the following does not qualify as an earth-excavating and hauling machine ?

Select your answer for: Which of the following does not qualify as an earth-excavating and hauling machine ?
Show answer

Answer: D. Dump truck

A dump truck is primarily classified as a hauling or transport vehicle rather than an excavator. Excavating machines dig and load earth, whereas dump trucks transport materials across sites. Earthmoving fleets combine ex...

Q4. Which listed item fails to qualify as a PERT event ?

Select your answer for: Which listed item fails to qualify as a PERT event ?
Show answer

Answer: D. class is being attended

An event in PERT represents a point in time or a milestone accomplishment. Class is being attended describes an ongoing activity rather than a static milestone event. Events consume zero time and resources, whereas atten...

Q5. Stratospheric ozone depletion may result in what environmental consequence___________________?

Select your answer for: Stratospheric ozone depletion may result in what environmental consequence___________________?
Show answer

Answer: B. Skin cancer

Stratospheric ozone acts as a crucial global shield absorbing harmful ultraviolet radiation from the sun. Depletion of this protective layer allows higher doses of UV-B radiation to reach the Earth surface. Excessive ult...

Q6. What is the correct logical progression for these activities________________?

Select your answer for: What is the correct logical progression for these activities________________?
Show answer

Answer: A. Concreting of roof slabs

Roof slabs must be fully concreted before subsequent structural layers or finishes can be placed. Concreting provides the structural deck required to support masonry parapet walls above. Logical construction sequencing d...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test