Question no. 16418

Project crashing during time-cost optimization is executed by____________?

Select your answer for: Project crashing during time-cost optimization is executed by____________?
Show answer

Answer: D. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Explanation

Crashing proceeds by targeting original critical activities and newly critical paths sequentially. Cost slopes dictate the order of crashing to ensure minimal financial investment for time saved. Newly formed critical paths must be crashed simultaneously alongside original critical path tasks. Project crashing is the process of shortening schedule duration by adding extra resources. Cost slope represents the additional financial cost incurred per unit of time saved. Time-cost optimization balances direct crashing costs against indirect overhead savings.

Construction managers crash schedules when contractual completion deadlines impose heavy financial penalties. Project owners evaluate crashing options to accelerate facility revenue generation capabilities. Engineers analyze cost slopes to determine the most economical activities for schedule compression. Option A is incorrect because crashing all project activities causes unnecessary financial expenditure. Option B fails to account for parallel paths becoming critical during the crashing process. Option C ignores new critical paths that emerge as initial critical tasks are shortened.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Within the referenced network diagram (Fig. 15), what is the latest start time for activity 4-5_________________?

Select your answer for: Within the referenced network diagram (Fig. 15), what is the latest start time for activity 4-5_________________?
Show answer

Answer: B. 4

Latest start time calculations involve backward passes through the network to determine critical time boundaries. Backward pass analysis subtracts activity durations from successor latest finish times methodically. Netwo...

Q2. For a constant bucket size, dragline productivity reaches its minimum when handling_______________?

Select your answer for: For a constant bucket size, dragline productivity reaches its minimum when handling_______________?
Show answer

Answer: D. Wet sticky clay

Wet sticky clay adheres to bucket walls and dumps poorly, reducing dragline productivity. Cohesive soils cling stubbornly to metal surfaces, increasing cycle times and lowering payloads. Material characteristics directly...

Q3. In CPM construction scheduling, Free Float can take values that are_____________?

Select your answer for: In CPM construction scheduling, Free Float can take values that are_____________?
Show answer

Answer: A. greater than Total Float.

Specialized network formulas and definitions can cause free float to mathematically exceed total float. Network configurations with multiple converging paths create unique mathematical relationships among float types. Th...

Q4. Contractors may receive a mobilization advance up to 10% of total work cost under the condition that_______________?

Select your answer for: Contractors may receive a mobilization advance up to 10% of total work cost under the condition that_______________?
Show answer

Answer: D. for all activities required to start the work at site on finalization of the contract document

Mobilization advances provide contractors with necessary initial capital after finalization of contract documents. Funds support preparatory site activities required to commence actual physical construction work efficien...

Q5. Manual earth excavation costs Rs. 10/cum. A machine operates with a Rs. 4000 fixed cost and Rs. 2/cum variable cost. At what earth volume do machine and manual excavation costs break even_________________?

Select your answer for: Manual earth excavation costs Rs. 10/cum. A machine operates with a Rs. 4000 fixed cost and Rs. 2/cum variable cost. At what earth volume do machine and manual excavation costs break even_________________?
Show answer

Answer: A. 500 cum

Equating manual cost to machine cost yields a break even volume of five hundred meters. Solving the linear equation ten V equals four thousand plus two V gives eight V. Dividing four thousand by eight results in exactly...

Q6. The latest start time for an activity is always________________?

Select your answer for: The latest start time for an activity is always________________?
Show answer

Answer: A. greater than or equal to latest event time of preceding node

Backward pass calculations ensure that latest start times respect preceding node timing constraints. The latest start time for any activity must exceed or equal its preceding event time. Network logic dictates that succe...