Network updating procedures may lead to_________________?
Show answer Hide answer
Answer: D. all of the above
Explanation
Network updating can reveal new critical paths, alter timelines, and change total duration. Updating incorporates actual site progress, modifying remaining task durations and logic. Unforeseen delays or accelerations frequently shift the critical path during project execution. Network updating is the periodic review and revision of project schedules using progress data. Actual completion dates replace original estimates for finished project activities. Remaining durations are reassessed for ongoing and future unstarted construction tasks.
Regular schedule updating is essential for maintaining control over complex construction projects. Project managers detect emerging bottlenecks early through systematic network updates. Accurate updating satisfies contractual reporting requirements and informs client stakeholders. Option A is incomplete because updating can also change project completion times. Option B is incomplete because updates can also increase overall project completion time. Option C is incomplete because updates can equally lead to shortened project completion times.
- Subject
- Engineering
- Category
- Civil Engineering
- Topic
- —
- Difficulty
- medium
Related questions
Q1. Shortening project completion time typically leads to_______________?
Show answer Hide answer
Answer: B. increasing the direct cost and decreasing the indirect cost
Crashing shortens duration, reducing indirect overhead costs while increasing direct crashing costs. Accelerating activities requires overtime wages and extra equipment, raising direct project expenses. Completing projec...
Q2. The schedule duration that yields the minimum overall project cost is defined as_______________?
Show answer Hide answer
Answer: D. between normal time and crash time
The overall minimum project cost typically occurs at an optimized schedule duration. This optimal duration falls somewhere between normal time and fully crashed schedule time. Balancing rising direct crash costs against...
Q3. The duration by which an activity can slip without disturbing preceding or succeeding tasks is termed_______________?
Show answer Hide answer
Answer: D. independent float
Independent float represents time an activity can slip without affecting preceding or succeeding tasks. This restrictive float metric measures maximum schedule independence for a single activity. It assumes all preceding...
Q4. What calculated value would you provide for the variance in the preceding scenario?
Show answer Hide answer
Answer: A. 81
Calculating the PERT variance formula for the referenced scenario yields eighty one. Subtracting optimistic time from pessimistic time and dividing by six gives fifteen. Squaring the resulting standard deviation value of...
Q5. The activity duration beyond which direct costs cease to decrease with added time is known as_________________?
Show answer Hide answer
Answer: B. normal time
Normal time represents the standard schedule duration required to complete an activity efficiently. Extending activity duration beyond normal time does not yield any further reduction in direct costs. Operating at normal...
Q6. Rubber-tired wheeled tractors are increasingly supplanting crawler tractors because________________?
Show answer Hide answer
Answer: A. wheeled tractors travel faster
Rubber tired wheeled tractors are preferred because they travel significantly faster between sites. Wheeled vehicles achieve higher transit speeds on paved roads than tracked crawler machines. Faster travel speeds reduce...