Question no. 18620

If ‘D’ represents the tunnel diameter in meters, the lining thickness in mm, derived from the empirical formula, is expressed as_________________?

Select your answer for: If ‘D’ represents the tunnel diameter in meters, the lining thickness in mm, derived from the empirical formula, is expressed as_________________?
Show answer

Answer: B. 82 D

Explanation

Empirical tunnel design formulas correlate concrete lining thickness directly with excavated tunnel diameter. Standard engineering practice for specific ground conditions yields the multiplier factor eighty-two in millimeters. Multiplying tunnel diameter D in meters by eighty-two gives the required preliminary lining thickness estimate. Tunnel lining thickness must resist external earth loads and internal service pressures safely. Empirical formulas provide rapid preliminary sizing estimates before detailed finite element analysis. Larger diameter tunnels require thicker concrete linings to prevent structural bending and buckling failures.

Civil engineers use empirical rules of thumb during early feasibility studies for major metro projects. Water conveyance tunnels apply similar thickness formulas to withstand internal hydrostatic bursting pressures. Final lining designs are always verified using detailed numerical stress modeling and geotechnical testing. Option A uses a smaller factor of forty-two, which results in dangerously thin lining dimensions. Option C applies a higher factor of one hundred four, leading to overly conservative concrete quantities. Option D suggests a factor of one hundred twenty-four, exceeding standard empirical thickness guidelines.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Assertion A : When geological rock conditions are favorable, concrete lining need not be installed concurrently with excavation until the entire tunnel has been driven. Reason R : Tunnels excavated through rock, whether hard or soft, never require concrete support lining________________JI?

Select your answer for: Assertion A : When geological rock conditions are favorable, concrete lining need not be installed concurrently with excavation until the entire tunnel has been driven. Reason R : Tunnels excavated through rock, whether hard or soft, never require concrete support lining________________JI?
Show answer

Answer: C. A is true but R is false

Favorable rock conditions allow stable temporary self-support, making immediate concrete lining unnecessary during excavation. However, weathering, stress redistribution, and seismic activity mean that rock tunnels event...

Q2. Assuming ‘N’ stands for the count of employed shafts, the aggregate working faces accessible for excavation and tunneling operations equal_________________________?

Select your answer for: Assuming ‘N’ stands for the count of employed shafts, the aggregate working faces accessible for excavation and tunneling operations equal_________________________?
Show answer

Answer: D. 2 N + 2

For N shafts, each shaft provides two working faces plus additional portal faces, leading to the formula 2N + 2 total working faces. Every intermediate vertical shaft opened along the tunnel alignment adds two opposing w...

Q3. The American method of tunneling is characterized by________________?

Select your answer for: The American method of tunneling is characterized by________________?
Show answer

Answer: A. only (i) is correct

The American method of tunneling relies on specific sequential timbering arrangements to support soft ground. Statement (i) correctly identifies the core timber framing characteristic unique to this historical technique....

Q4. Within compressed air tunneling procedures, the quantity of uncompressed air supplied is______________?

Select your answer for: Within compressed air tunneling procedures, the quantity of uncompressed air supplied is______________?
Show answer

Answer: B. 6 m3 per minute per m2 of face area

Compressed air tunneling standards specify generous ventilation volumes to maintain safe worker oxygen levels. The required uncompressed air supply rate is six cubic meters per minute per square meter of face area. Adequ...

Q5. What is the correct operational sequence of drilling equipment used to enlarge blast hole sizes in tunneling________________?

Select your answer for: What is the correct operational sequence of drilling equipment used to enlarge blast hole sizes in tunneling________________?
Show answer

Answer: A. wagon drill, churn drill, shot drill

Blast hole enlargement requires a progressive sequence of drilling machinery tailored to increasing hole diameters. Operations typically begin with wagon drills for smaller initial pilot holes before moving to heavier eq...

Q6. Compared to having only one free face, positioning an explosive charge equidistant from two separate faces results in a yield that___________________?

Select your answer for: Compared to having only one free face, positioning an explosive charge equidistant from two separate faces results in a yield that___________________?
Show answer

Answer: C. increases by 2.25 times

Placing an explosive charge equidistant from two free faces creates intersecting blast fracture planes. This multi-directional relief increases rock fragmentation efficiency, raising overall blast yield significantly. Em...