Question no. 17319

If a grit chamber has a design flow velocity of 0.2 m/sec and a detention period of 2 minutes, what is its required length__________________?

Select your answer for: If a grit chamber has a design flow velocity of 0.2 m/sec and a detention period of 2 minutes, what is its required length__________________?
Show answer

Answer: C. 24 m

Explanation

Required length equals the product of design flow velocity and the specified detention time duration. Multiplying 0.2 meters per second by 120 seconds yields a total calculated chamber length of 24 meters. This dimensional calculation ensures grit particles have sufficient horizontal travel time to settle out. Grit chambers remove heavy inorganic sand and gravel to protect mechanical equipment from abrasive wear. Detention period represents the average time a given wastewater volume remains inside the treatment tank. Maintaining controlled horizontal velocities prevents organic matter from settling alongside heavier grit particles.

Municipal sewage treatment plants utilize grit removal channels at the headworks of every facility. Properly sized grit chambers prevent pipeline blockages and pump impeller damage throughout the plant. Environmental engineers design these basins to handle peak hourly wet-weather stormwater flow surges. A length of 16 meters underestimates the required settling distance for the given velocity and time. A length of 20 meters results from incorrect time conversion math during preliminary sizing calculations. A length of 30 meters exceeds the required dimensions, leading to unnecessary construction and land costs.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. What characterizes the wake zone behind an object_______________?

Select your answer for: What characterizes the wake zone behind an object_______________?
Show answer

Answer: B. always occurs after a separation point

Flow separation occurs when adverse pressure gradients force boundary layers to detach from solid surfaces. The separated fluid layer rolls up into chaotic eddies, forming a distinct wake zone immediately downstream. Thi...

Q2. What proportion of total water consumption is typically assumed for sewage discharge during sewer design_____________________?

Select your answer for: What proportion of total water consumption is typically assumed for sewage discharge during sewer design_____________________?
Show answer

Answer: C. 75 to 80%

Standard sanitary sewer design assumes that approximately 75 to 80% of total consumed water reaches sewers. Water lost through lawn watering, evaporation, and industrial consumption never enters the drainage network. Emp...

Q3. What chemical reagent is introduced to produce a matching color for nitrite detection in sewage_________________?

Select your answer for: What chemical reagent is introduced to produce a matching color for nitrite detection in sewage_________________?
Show answer

Answer: B. Sulphuric acid and napthamine

Chemical testing of sewage requires specific reagents to react selectively with targeted nitrogen compounds. Sulfuric acid provides the necessary acidic medium for diazotization and subsequent color development reactions...

Q4. What standard groundwater infiltration rate into sewers is assumed for design purposes___________________?

Select your answer for: What standard groundwater infiltration rate into sewers is assumed for design purposes___________________?
Show answer

Answer: D. 2000 litres/km/cm

Sewer design standards incorporate safety allowances for groundwater leaking inward through pipe joints. Infiltration rates depend on pipe length, diameter, and local groundwater table elevation pressures. Standard munic...

Q5. What test is performed on building drainage pipes prior to operational use__________________?

Select your answer for: What test is performed on building drainage pipes prior to operational use__________________?
Show answer

Answer: B. Smoke test

A smoke test is commonly performed on newly installed building drainage and vent pipes to check for leaks. Smoke is pumped through the drainage system under low pressure to reveal faulty joints or cracks. Any escaping sm...

Q6. What is the maximum permissible distance between manholes on large sewer lines_______________?

Select your answer for: What is the maximum permissible distance between manholes on large sewer lines_______________?
Show answer

Answer: D. 300 m

Access manholes allow maintenance crews to inspect, clean, and clear blockages in large sewer networks. Large trunk lines have greater flow capacities and fewer obstruction risks than small branch sewers. Design codes pe...

New!

Mock Test System is now available!

Prepare for your exam with interactive mock tests. Select your subjects, attempt 100 random MCQs against the clock, and see exactly where you stand.

Start Mock Test