Skip to main content
Sign in Register
Question no. 17580

If a 10% risk of flooding is acceptable over the next 10 years, what design return period should be selected__________________?

Select your answer for: If a 10% risk of flooding is acceptable over the next 10 years, what design return period should be selected__________________?
Show answer

Answer: C. 1/(1-0.9°10)

Explanation

Flood risk probability formulas relate acceptable risk r, design life n, and return period t. The exact binomial risk equation transforms to solve for the return period t parameter. Algebraic rearrangement yields the exact mathematical expression presented in option C. Return period represents the statistical average time interval between floods of a given magnitude. Hydrological risk is the probability that a flood of specified size will occur at least once in n years. Engineers balance economic costs against acceptable flood risk probabilities when sizing structures.

Dam spillways and urban drainage systems are designed using specific return period flood thresholds. Risk analysis helps municipalities quantify infrastructure vulnerability to extreme weather events. Probability calculations ensure public safety while optimizing capital investment in flood defenses. Option A provides an incorrect mathematical structure lacking proper probability exponents. Option B fails to represent the correct algebraic inversion required for return period formulas. Option D includes an erroneous plus sign in the denominator violating binomial probability rules.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. How do earthen dams compare structurally to concrete gravity dams__________________?

Select your answer for: How do earthen dams compare structurally to concrete gravity dams__________________?
Show answer

Answer: D. require less skilled labour

Earthen dams are constructed primarily using locally excavated soils compacted by heavy earthmoving machinery. Unlike precision concrete gravity dams, earthen structures do not demand highly specialized formwork labor. C...

Q2. If rainfall occurs between 2 P.M. and 3 P.M. and runoff reaches the basin outlet starting at 3 P.M., what is the time of concentration_____________________?

Select your answer for: If rainfall occurs between 2 P.M. and 3 P.M. and runoff reaches the basin outlet starting at 3 P.M., what is the time of concentration_____________________?
Show answer

Answer: D. 60 minutes

Time of concentration measures the travel duration from the most hydraulically remote watershed point to the outlet. Runoff begins reaching the basin outlet sixty minutes after the rainfall event starts. The elapsed time...

Q3. If a canal bed level is 212.0 m and the crossing drainage high flood level is 210.0 m, what type of cross-drainage structure is required________________?

Select your answer for: If a canal bed level is 212.0 m and the crossing drainage high flood level is 210.0 m, what type of cross-drainage structure is required________________?
Show answer

Answer: C. syphon

Cross drainage structures are required when an irrigation canal intersects a natural drainage stream. Here the canal bed level is higher than the drainage high flood level, allowing gravity flow. However, because drainag...

Q4. How is infiltration capacity defined_________________?

Select your answer for: How is infiltration capacity defined_________________?
Show answer

Answer: D. changes with both time and location

Infiltration capacity varies dynamically across a catchment depending on soil moisture and spatial location. Different locations possess unique soil compositions and vegetation covers that influence local infiltration ra...

Q5. What effect does horizontal seismic acceleration produce in structures______________?

Select your answer for: What effect does horizontal seismic acceleration produce in structures______________?
Show answer

Answer: C. both (A) and (B)

Horizontal seismic ground acceleration forces push horizontally against the rigid body of concrete dams. Inertia forces develop within the dam mass proportional to structural mass and seismic acceleration. Simultaneously...

Q6. What does an instantaneous unit hydrograph represent________________?

Select your answer for: What does an instantaneous unit hydrograph represent________________?
Show answer

Answer: A. unit duration

An instantaneous unit hydrograph represents direct runoff resulting from a unit rainfall excess applied instantly. The theoretical concept assumes the rainfall duration approaches zero to isolate pure catchment response...