Chain measurements across rugged or hilly terrain have a permissible error limit of_____________?

Select your answer for: Chain measurements across rugged or hilly terrain have a permissible error limit of_____________?
Show answer

Answer: B. 1 in 250

Explanation

Chain measurements across rugged or hilly terrain have a permissible error limit of 1 in 250. Rough topography makes precise horizontal chaining difficult due to slope breaks and physical obstacles. Survey specifications relax allowable closure limits for difficult terrain compared to flat open ground. Chain surveying accuracy is expressed as a ratio of the misclosure error to the total measured distance. Hilly terrain requires breaking the chain, using plumb bobs, and applying rigorous slope corrections. Despite precautions, uneven ground introduces physical errors that justify a higher permissible limit.

Preliminary route surveys across mountainous country rely on chains where high-end EDMs are unavailable. Civil engineering contracts specify exact permissible error limits to determine acceptable survey quality. Exceeding the 1 in 250 limit forces field crews to rechain the section to ensure data reliability. Option 1 in 100 represents an excessively loose error limit that would result in unacceptable survey quality. Option 1 in 500 is specified for flat open country with ideal weather and chaining conditions. Option 1 in 1000 demands high-precision base measurements using steel tapes rather than standard chains.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. What survey measurements are recorded at a shifting station or turning point________________?

Select your answer for: What survey measurements are recorded at a shifting station or turning point________________?
Show answer

Answer: C. foresight and backsight

A shifting or turning point in differential leveling serves as a temporary benchmark between setups. At this location, the surveyor records both a foresight from the old instrument position and a backsight. This dual rea...

Q2. Surveyor's compasses and prismatic compasses differ in that________________?

Select your answer for: Surveyor's compasses and prismatic compasses differ in that________________?
Show answer

Answer: A. give whole circle bearing (WCB. of a line and quadrantal bearing (QB. of a line respectively

Surveyor compasses give quadrantal bearings while prismatic compasses give whole circle bearings. Prismatic compasses use a magnetic ring reading from zero to three60 degrees clockwise. Surveyor compasses use a quadrant...

Q3. Determining instrument station coordinates by drawing intersecting rays from known stations is called_________________?

Select your answer for: Determining instrument station coordinates by drawing intersecting rays from known stations is called_________________?
Show answer

Answer: C. resection

Resection is the method of determining an unknown instrument station by sighting known points. Drawing intersecting rays from visible control stations allows the surveyor to fix their position. This technique is widely u...

Q4. Bubble tube sensitivity can be enhanced by________________?

Select your answer for: Bubble tube sensitivity can be enhanced by________________?
Show answer

Answer: A. increasing the diameter of the tube

The sensitivity of a bubble tube is enhanced by increasing the diameter of the tube. A larger tube diameter allows for a larger radius of curvature on the internal upper glass surface. This geometric adjustment makes the...

Q5. Plane table dimensions are standardized as________________?

Select your answer for: Plane table dimensions are standardized as________________?
Show answer

Answer: B. 600 mm x 750 mm

Drawing board dimensions for standard plane tables are officially specified as 600 mm by 750 mm. Manufacturing standards ensure these specific dimensions provide adequate working space for field mapping. The board size b...

Q6. The rise and fall calculation method_______________?

Select your answer for: The rise and fall calculation method_______________?
Show answer

Answer: C. provides a check on the reduction of intermediate point levels

The rise and fall calculation method provides an explicit mathematical check on intermediate point levels. It compares every consecutive point to calculate elevation differences directly as rises or falls. This rigorous...