Question no. 16433

A 12.5-tonne tractor develops a maximum first-gear rimpull of 6300 kg on a 2% upgrade with a 45 kg/tonne rolling resistance. Determine the towing pull available for a load________________?

Select your answer for: A 12.5-tonne tractor develops a maximum first-gear rimpull of 6300 kg on a 2% upgrade with a 45 kg/tonne rolling resistance. Determine the towing pull available for a load________________?
Show answer

Answer: B. 5515 kg

Explanation

Subtracting grade and rolling resistance losses from total rimpull leaves net towing pull. Resistance forces acting against the tractor reduce the available drawbar pulling capacity. Calculating grade and rolling resistance values allows accurate net pulling force determination. Rimpull is the tractive force developed between rubber tires and the driving surface. Grade resistance opposes vehicle movement on upgrades proportional to total vehicle weight. Rolling resistance accounts for tire flexing and surface deformation losses during travel.

Earthmoving contractors calculate net towing pull to ensure tractors can haul loaded scrapers. Accurate performance sizing prevents equipment stalls and maintains high site productivity. Job site slopes and soil conditions dictate the effective hauling capacity of heavy machinery. Option A underestimates available towing pull due to an incorrect resistance subtraction. Option C overestimates towing pull by ignoring specific grade resistance components. Option D results from improper calculation of tire rimpull and surface resistance losses.

Subject
Engineering
Topic
—
Difficulty
medium

Related questions

Q1. Interfering float is calculated as the difference between__________________?

Select your answer for: Interfering float is calculated as the difference between__________________?
Show answer

Answer: A. total float and free float

Interfering float is defined mathematically as the difference between total and free float. This float metric indicates how much an activity delay impinges upon successor total float. Subtracting free float from total fl...

Q2. The area under a Beta probability distribution curve is bisected into equal halves by_______________?

Select your answer for: The area under a Beta probability distribution curve is bisected into equal halves by_______________?
Show answer

Answer: D. expected time

The expected time in a Beta distribution curve divides the probability area into two equal halves. Probability curves for PERT duration estimates are balanced around this calculated expected time value. Mathematical inte...

Q3. Sensitivity analysis investigates__________________?

Select your answer for: Sensitivity analysis investigates__________________?
Show answer

Answer: C. change in output due to change in input

Sensitivity analysis investigates how changes in input parameters affect project model outputs. This analytical technique identifies which variables exert the greatest influence on results. Testing various input scenario...

Q4. What is the normal project completion duration established in the preceding problem_______________?

Select your answer for: What is the normal project completion duration established in the preceding problem_______________?
Show answer

Answer: C. 14 days

Network path analysis determines the normal project completion duration to be fourteen days. Summing activity durations along the critical path yields the total project completion time. Critical path calculations identif...

Q5. What is the statistical probability that any activity finishes within its expected duration_________________?

Select your answer for: What is the statistical probability that any activity finishes within its expected duration_________________?
Show answer

Answer: A. 50%

Due to curve symmetry around expected duration, the probability of finishing within it is fifty percent. Normal and beta probability distributions divide equally at their central expected mean value. There is an equal st...

Q6. The direct cost associated with a project executed in normal time is designated as________________?

Select your answer for: The direct cost associated with a project executed in normal time is designated as________________?
Show answer

Answer: A. minimum

Executing a project in normal time allows work to proceed at an uncompressed pace. Operating at normal speed minimizes direct labor and equipment overtime premium costs. Normal duration represents the most cost-effective...